Off-Line Commissioning 75
TRX Diagnostics
This section explains how to use the Craft PC to run the TRX POST diagnostics on the WAVEXpress/BTS locally.
Step 1
After the WAVEXpress/BTS has bootup and the T1 POST has run during the boot process, the TRX
POST diagnostics can be initiated. Type:
bts:A->
runtrxpost
[ENTER]
Step 2
A set of 40 TRX POST diagnostics will run sequentially and the results of each test will be listed as
PASSED/FAILED. Only if all 40 tests passed successfully will the TRX POST diagnostics be considered
successful. The TRX POST results will be displayed after the boot process have been completed:
The following example shows the TRX POST results of a 2 TRX BTS. The format for each diagnostic line
is:
[line number][action][TRX number][test number][description of the test][test result].
For example:
19 (Diag) TRX(4) TF22: Test Basic op of VME/RTP FIFOs: PASSED
where:
NOTE
The TRX on-line LED flashes continuously when TRX POST diagnostics are being run
and does not stop flashing until the WAVEXpress/BTS is rebooted. The flashing LED
can be used as a reminder to reboot the system after successfully completing the TRX
POST diagnostics.
Table 4-3: Description of the TRX POST results
Line Entry Description
19 Line number
Diag Diagnostic test being run
TRX 4 TRX4 being tested
TF22 Test number
Test Basic op of VME/RTP FIFOs Test description
PASSED Indicates that the TRX passed this test.