Installation Manual
Table Of Contents
- WAVEXpress/BTS Installation and Commissioning Guide
- One - Unpacking the WAVEXpress/BTS
- Two - Internal BTS Cabling and Jumpering
- Three - Installation
- 3-1 Wall Installation
- 3-2 Table Mount
- 3-3 Rack Installation
- 3-4 Common Final Installation Procedures
- 3-4.1 Connection of the Cable Gland
- 3-4.2 Connection of the Grounding Cable
- 3-4.3 Connection of the Antennas to the Bulkhead Plate
- 3-4.4 Connection of the Optional Combiner Assembly
- 3-4.5 Connection of the Power Supply
- 3-4.6 Connection of the T1 Lines
- 3-4.7 Connection to External Alarms
- 3-4.8 Optional Voltage Standing Wave Ratio (VSWR) Check
- 3-4.9 Post Installation Checks
- 3-5 Outdoor Installation
- Four - Off-Line Commissioning
- Five - Off-Line Commissioning of a Daisy Chain
- Six - Post Off-Line Commissioning
- Seven - On-Line Commissioning
- Appendix 1 - Connection of the Combiner Assembly
- Appendix 2 - BTS Field Maintenance
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- A2-1.1 Replacing the WAVEXpress/BTS IWP card
- A2-1.2 Replacing the WAVEXpress/BTS T1 card
- A2-1.3 Replacing the WAVEXpress/BTS TRX card
- A2-1.4 Replacing the WAVEXpress/BTS RF distribution card
- A2-1.5 Replacing the clock module
- A2-1.6 Replacing power supply units
- A2-1.7 Replacing fan assemblies
- A2-1.8 Replacing filters (p/n 520081-01)
- A2-1.9 Replacing the antenna bracket with a combiner assembly
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- Checklist 1 - Installation Checklist
- Checklist 2 - Commissioning Checklist
Release 3.3, Revision A 1/99
Off-Line Commissioning 67
The final LED sequence should be:
If your display is different than what is shown, refer to the BSS Maintenance Guide
.
4-2.2 Power On Self Test (POST) Diagnostics
Power-on self tests (POST) are optional diagnostics designed to exercise the hardware cards and modules, to the
component level, in order to detect and report any problems.
POST diagnostics are currently run upon start-up on the T1 card, and can be invoked off-line for both the T1 and TRX
cards. The following section describes the recommended sequence of steps which should be performed in order to
check that the Craft PC can be connected to the BTS over an Ethernet connection, that the correct version of code is
loaded from the Craft PC to the BTS and that the POST diagnostics are run successfully.
Connection of the Craft PC to the BTS
Required Hardware
The following hardware is needed to connect the Craft PC to the WAVEXpress/BTS through an Ethernet and a serial
connection. Note that this hardware is supplied with the Craft PC:
• 1 RG-58 coaxial cable terminating in BNC connectors
• 2 50-Ohm terminators with BNC connectors
• 2 BNC T-connectors
• 1 3Com Combo transceiver
• 1 AUI-BNC transceiver.
• 1 DB9 cable (male to female)
Table 4-1: WAVEXpress/BTS LED indications
LED DESCRIPTION
SCN Green LED, lit when IWP is operational (only present on the IWP card)
PWR
Green LED, lit when card has power supplied.
The PWR LED of the IWP, T1 and TRX card will be lit after all cards have completed
the boot-up process.
On-Line
Green LED, lit when card is on-line, and module BOOT process has been
performed successfully.
The On-Line LED of the IWP, T1 and TRX cards will be lit after all cards have
completed the boot-up process.
Flt
Red LED, lit when card detects a fault or is not downloaded.
No FLT LEDs should be lit if the boot-up process is successful.