60 WAVEXpress/BTS Installation and Commissioning Guide
3-5.5 Post Installation Checks
BTS Connection
Prior to commissioning the WAVEXpress/BTS, make sure that:
The Abis interface T1 dual port cables are routed to the local T1 provider.
Ensure that the DIP switch setting on the T1 card is set correctly. The length of T1 cables should
be taken into account and the proper impedence set on the T1 card using the T1 dip switch.
Refer to Section 2.3 T1 dip switch settings.
The BTS' power is turned off.
BTS-BSC Link Verification
It is the operator's responsibility to verify that all BTS-BSC T1 links are ordered, installed and cer-
tified according to ANSI T1.403 specifications before on-line commissioning is performed.
The operator should also perform end-to-end bit error rate tests over a 20 minute period on the
T1 Abis interface link.