Installation Manual
Table Of Contents
- WAVEXpress/BTS Installation and Commissioning Guide
- One - Unpacking the WAVEXpress/BTS
- Two - Internal BTS Cabling and Jumpering
- Three - Installation
- 3-1 Wall Installation
- 3-2 Table Mount
- 3-3 Rack Installation
- 3-4 Common Final Installation Procedures
- 3-4.1 Connection of the Cable Gland
- 3-4.2 Connection of the Grounding Cable
- 3-4.3 Connection of the Antennas to the Bulkhead Plate
- 3-4.4 Connection of the Optional Combiner Assembly
- 3-4.5 Connection of the Power Supply
- 3-4.6 Connection of the T1 Lines
- 3-4.7 Connection to External Alarms
- 3-4.8 Optional Voltage Standing Wave Ratio (VSWR) Check
- 3-4.9 Post Installation Checks
- 3-5 Outdoor Installation
- Four - Off-Line Commissioning
- Five - Off-Line Commissioning of a Daisy Chain
- Six - Post Off-Line Commissioning
- Seven - On-Line Commissioning
- Appendix 1 - Connection of the Combiner Assembly
- Appendix 2 - BTS Field Maintenance
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- A2-1.1 Replacing the WAVEXpress/BTS IWP card
- A2-1.2 Replacing the WAVEXpress/BTS T1 card
- A2-1.3 Replacing the WAVEXpress/BTS TRX card
- A2-1.4 Replacing the WAVEXpress/BTS RF distribution card
- A2-1.5 Replacing the clock module
- A2-1.6 Replacing power supply units
- A2-1.7 Replacing fan assemblies
- A2-1.8 Replacing filters (p/n 520081-01)
- A2-1.9 Replacing the antenna bracket with a combiner assembly
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- Checklist 1 - Installation Checklist
- Checklist 2 - Commissioning Checklist
Release 3.3, Revision A 1/99
Installation 55
Step 3
Thread the cable over the top of the swing frame, and attach the other end of this cable to the top SMA
connector of the hybrid combiner. (Cable labeled as #1 in Figure 3-19)
Step 4
Attach one end of the second cable (part numbers 740060) to the Transmit port labeled Tx on the TRX
card in slot 4 and 5 of the WAVEXpress/BTS chassis. (Cable labeled as #2 in Figure 3-18)
Step 5
Thread the cable over the top of the swing frame, and attach the other end of this cable to the bottom
SMA connector of the hybrid combiner. (Cable labeled as #2 in Figure 3-18)
Step 6
Locate the two cables marked with part numbers 740054, and having a SMA connector at one end and a
N-type connector at the other end. (Cable labeled as #3 in Figure 3-18)
Step 7
Attach the SMA connector of one of these cables (part numbers 740054) to the antenna port labeled -1-
on the RF Distribution card.
Step 8
Thread the cable over the top of the swing frame, and attach the other end of this cable to the N-type
connector of the first receive filter. (Cable labeled as #3 in Figure 3-18)
Step 9
Attach the SMA connector of one of these cables (part numbers 740054) to the antenna port labeled -2-
on the RF Distribution card. (Cable labeled as #4 in Figure 3-19)
Step 10
Thread the cable over the top of the swing frame, and attach the other end of this cable to the N-type
connector of the second receive filter. (Cable labeled as #4 in Figure 3-18)
Step 11
Thread the customer supplied antenna cables through the conduit located at the bottom of the enclo-
sure.
Step 12
Connect each of the customer supplied antenna cables to the two receive filters. (Cable labeled as #5 in
Figure 3-18)
Step 13
Connect the third antenna cable to the transmit filter. (Cable labeled as #6 in Figure 3-18).