Installation Manual

Table Of Contents
Release 3.3, Revision A 1/99
Commissioning Checklist 135
3 __
Database questionnaire completed with BTS parameters defined
4 __
OMC downloaded BTS configuration with correct operational parameters
5 __
RF frequencies cleared to transmit
6 __
BTS T1 module’s cables connected to the local T1 Provider demarcation
7 __
BSC T1 module’s cables connected to the local T1 Provider demarcation assigned to the BTS
Note: Operator’s responsibility to verify all E1 links properly installed and certified by local T1 Provider
facilities. Certification must rate: Length of testing and BER results
BTS-BSC Network Integration
1 __
Unlock the Abis interface
2 __
Unlock the BTS
3 __
Verify the BTS’ operational state
Recovery
1 __
Perform a BTS cold start and verify that the BTS fully recovers
2 __
Confirm Abis interface re-establishes communications to BSC after T1 disconnects
Operational tests
1 __
Unlock TRX
2 __
Perform test calls on each timeslot
3 __
Perform test calls on each TRX
Final commissioning, on-line tests
1 __
Leave power to BTS on
2 __
Inform the OMC operator that commissioning is complete