Installation Manual
Table Of Contents
- WAVEXpress/BTS Installation and Commissioning Guide
- One - Unpacking the WAVEXpress/BTS
- Two - Internal BTS Cabling and Jumpering
- Three - Installation
- 3-1 Wall Installation
- 3-2 Table Mount
- 3-3 Rack Installation
- 3-4 Common Final Installation Procedures
- 3-4.1 Connection of the Cable Gland
- 3-4.2 Connection of the Grounding Cable
- 3-4.3 Connection of the Antennas to the Bulkhead Plate
- 3-4.4 Connection of the Optional Combiner Assembly
- 3-4.5 Connection of the Power Supply
- 3-4.6 Connection of the T1 Lines
- 3-4.7 Connection to External Alarms
- 3-4.8 Optional Voltage Standing Wave Ratio (VSWR) Check
- 3-4.9 Post Installation Checks
- 3-5 Outdoor Installation
- Four - Off-Line Commissioning
- Five - Off-Line Commissioning of a Daisy Chain
- Six - Post Off-Line Commissioning
- Seven - On-Line Commissioning
- Appendix 1 - Connection of the Combiner Assembly
- Appendix 2 - BTS Field Maintenance
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- A2-1.1 Replacing the WAVEXpress/BTS IWP card
- A2-1.2 Replacing the WAVEXpress/BTS T1 card
- A2-1.3 Replacing the WAVEXpress/BTS TRX card
- A2-1.4 Replacing the WAVEXpress/BTS RF distribution card
- A2-1.5 Replacing the clock module
- A2-1.6 Replacing power supply units
- A2-1.7 Replacing fan assemblies
- A2-1.8 Replacing filters (p/n 520081-01)
- A2-1.9 Replacing the antenna bracket with a combiner assembly
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- Checklist 1 - Installation Checklist
- Checklist 2 - Commissioning Checklist
Release 3.3, Revision A 1/99
134 WAVEXpress/BTS Installation and Commissioning Guide
BTS off-line software checks
1 __
Connect the Craft PC to the BTS using a serial and Ethernet cable
2 __
Establish a serial connection
3 __
Check BTS boot parameters
4 __
Check the IWP flash version number
POST tests
1 __
Verify T1 POST tests successfully passed
2 __
Verify TRX POST tests successfully passed for each module
TRX Commissioning
1 __
Connect the BTS to the Craft PC and the Racal testset
2 __
Start the Racal
3 __
Load the sequence files on to the PCMCIA card from the CD-ROM
4 __
Setup the test results presentation on the Racal
5 __
Set the offset values for RF cable loss
6 __
Run the automated test sequence
TRX 1 Pass
Fail
TRX 2 Pass Fail
TRX 3 Pass Fail
Post Racal Procedures
1 __
Disconnect the BTS from the Racal testset
2 __
Reboot the BTS using the Craft PC
3 __
Disconnect the BTS from the Craft PC
Post off-line commissioning
At the Depot
1 __
Physically install BTS on-site
2 __
Connect T1 lines to T1 Provider demarcation point
3 __
Leave power to BTS on
4 __
Inform OMC operator that BTS is ready for on-line commissioning
On-Site
1 __
Connect T1 lines to T1 Provider demarcation point
2 __
Leave power to BTS on
3 __
Inform OMC operator that BTS is ready for on-line commissioning
On-Line Commissioning
BTS on-line commissioning pre-requisites
1 __
BSC in service and connected to BTS
2 __
OMC in service and connected to BSC