Commissioning Checklist
Off-Line Commissioning
Pre-commissioning visual checks
At the Depot
2 __
Power to BTS is off
3 __
BTS connected to power source
4 __
BTS grounded
5 __
Equipment cables labeled and secured
6 __
Cards seated securely
On-Site
1 __
Installation secure
2 __
Power to BTS is off
3 __
BTS connected to power source
4 __
BTS grounded
5 __
Equipment cables labeled and secured
6 __
Cards seated securely
7 __
Transmission cables available and labeled
Compliance check
1 __
Cross check with site specific data to ensure BTS is correctly configured with all cards
2 __
Serial number of all cards recorded
3 __
Verify correct operating voltage supplied: 230V 115V -48V
Power on
1 __
Disconnect all T1 cables from BTS (if connected)
2 __
Turn power to BTS on
3 __
All card power LEDs and IWP and E1 on-line LEDs are green
Site name
Address
BSC name
MSC name
Site/Access phone number