Installation Manual

Table Of Contents
Release 3.3, Revision A 1/99
132 WAVEXpress/BTS Installation and Commissioning Guide
Wall mount (if applicable)
1 __
Mount wall attachment plate
2 __
Mount chassis to wall attachment plate
3 __
Attach chassis door (if detached)
4 __
Ground chassis
5 __
Connect power supply: 115V, 230V, -48V
Table mount (if applicable)
1 __
Mount chassis in table mount
2 __
Ground chassis
3 __
Connect power supply: 115V, 230V, -48V
Rack mount (if applicable)
1 __
Attach mounting brackets to chassis
2 __
Mount chassis in rack
3 __
Ground chassis
4 __
Connect power supply: 115V 230V -48V
Outdoor enclosure mount (if applicable)
1 __
Mount enclosure to surface
2 __
Install all internal cabling
3 __
Connect power supply: 115V 230V -48V
4 __
Install mounting plate into the swing frame
5 __
Install BTS into swing frame
6 __
Connect and route data and antenna cables
VSWR Check
VSWR measurements are performed by the operator to verify the installation of external antennas.
1 __
VSWR measurement on TX antenna #1
2 __
VSWR measurement on TX antenna #2 (if applicable)
3 __
VSWR measurement on TX antenna #3 (if applicable)
BTS connection
1 __
Connect “Abis Interface” T1 dual port cables to local T1 Provider demarcation
2 __
Configure dual port T1 card DIP switch settings
3 __
Ensure power to BTS is off.
BTS-BSC link verification
It is the operator’s responsibility to verify that all BTS-BSC T1 links are ordered, installed and certified by the local
TELCO facilities/operator.
1 __
Verify bit error rates on a nominal 20 minute soak test on the E1 Abis-interface (end-to-end BER test to
include dual port T1 cables)