Installation Manual

Table Of Contents
Release 3.3, Revision A 1/99
BTS Field Maintenance 115
Step 8
Using a torque wrench (set to 8 in. lbs.), reconnect all disconnected RF cables to the new TRX card.
Step 9
The replacement TRX card should begin to download automatically.
Step 10
Inform the OMC operator to unlock the replacement TRX card.
Step 11
Inform the OMC operator to verify the status of the replacement TRX card. The following table contains
a list of the status values of an operational TRX card. The status of the replacement TRX card should
contain the values listed below.
Step 12
Once the TRX card is replaced and is operational, TRX POST diagnostics will run automatically. Inform
the OMC operator to verify if the replacement TRX card passed POST successfully.
Step 13
Conduct test calls on all TRX channels contained in the WAVEXpress/BTS.
Table A2-2:
Operational TRX card status
Attribute Status
AdminState ADMIN_UNLOCKED
OperStatus OPERATION_ENABLED
AvailStatus ON_LINE