Installation Manual
Table Of Contents
- WAVEXpress/BTS Installation and Commissioning Guide
- One - Unpacking the WAVEXpress/BTS
- Two - Internal BTS Cabling and Jumpering
- Three - Installation
- 3-1 Wall Installation
- 3-2 Table Mount
- 3-3 Rack Installation
- 3-4 Common Final Installation Procedures
- 3-4.1 Connection of the Cable Gland
- 3-4.2 Connection of the Grounding Cable
- 3-4.3 Connection of the Antennas to the Bulkhead Plate
- 3-4.4 Connection of the Optional Combiner Assembly
- 3-4.5 Connection of the Power Supply
- 3-4.6 Connection of the T1 Lines
- 3-4.7 Connection to External Alarms
- 3-4.8 Optional Voltage Standing Wave Ratio (VSWR) Check
- 3-4.9 Post Installation Checks
- 3-5 Outdoor Installation
- Four - Off-Line Commissioning
- Five - Off-Line Commissioning of a Daisy Chain
- Six - Post Off-Line Commissioning
- Seven - On-Line Commissioning
- Appendix 1 - Connection of the Combiner Assembly
- Appendix 2 - BTS Field Maintenance
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- A2-1.1 Replacing the WAVEXpress/BTS IWP card
- A2-1.2 Replacing the WAVEXpress/BTS T1 card
- A2-1.3 Replacing the WAVEXpress/BTS TRX card
- A2-1.4 Replacing the WAVEXpress/BTS RF distribution card
- A2-1.5 Replacing the clock module
- A2-1.6 Replacing power supply units
- A2-1.7 Replacing fan assemblies
- A2-1.8 Replacing filters (p/n 520081-01)
- A2-1.9 Replacing the antenna bracket with a combiner assembly
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- Checklist 1 - Installation Checklist
- Checklist 2 - Commissioning Checklist
Release 3.3, Revision A 1/99
BTS Field Maintenance 115
Step 8
Using a torque wrench (set to 8 in. lbs.), reconnect all disconnected RF cables to the new TRX card.
Step 9
The replacement TRX card should begin to download automatically.
Step 10
Inform the OMC operator to unlock the replacement TRX card.
Step 11
Inform the OMC operator to verify the status of the replacement TRX card. The following table contains
a list of the status values of an operational TRX card. The status of the replacement TRX card should
contain the values listed below.
Step 12
Once the TRX card is replaced and is operational, TRX POST diagnostics will run automatically. Inform
the OMC operator to verify if the replacement TRX card passed POST successfully.
Step 13
Conduct test calls on all TRX channels contained in the WAVEXpress/BTS.
Table A2-2:
Operational TRX card status
Attribute Status
AdminState ADMIN_UNLOCKED
OperStatus OPERATION_ENABLED
AvailStatus ON_LINE