Installation Manual
Table Of Contents
- WAVEXpress/BTS Installation and Commissioning Guide
- One - Unpacking the WAVEXpress/BTS
- Two - Internal BTS Cabling and Jumpering
- Three - Installation
- 3-1 Wall Installation
- 3-2 Table Mount
- 3-3 Rack Installation
- 3-4 Common Final Installation Procedures
- 3-4.1 Connection of the Cable Gland
- 3-4.2 Connection of the Grounding Cable
- 3-4.3 Connection of the Antennas to the Bulkhead Plate
- 3-4.4 Connection of the Optional Combiner Assembly
- 3-4.5 Connection of the Power Supply
- 3-4.6 Connection of the T1 Lines
- 3-4.7 Connection to External Alarms
- 3-4.8 Optional Voltage Standing Wave Ratio (VSWR) Check
- 3-4.9 Post Installation Checks
- 3-5 Outdoor Installation
- Four - Off-Line Commissioning
- Five - Off-Line Commissioning of a Daisy Chain
- Six - Post Off-Line Commissioning
- Seven - On-Line Commissioning
- Appendix 1 - Connection of the Combiner Assembly
- Appendix 2 - BTS Field Maintenance
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- A2-1.1 Replacing the WAVEXpress/BTS IWP card
- A2-1.2 Replacing the WAVEXpress/BTS T1 card
- A2-1.3 Replacing the WAVEXpress/BTS TRX card
- A2-1.4 Replacing the WAVEXpress/BTS RF distribution card
- A2-1.5 Replacing the clock module
- A2-1.6 Replacing power supply units
- A2-1.7 Replacing fan assemblies
- A2-1.8 Replacing filters (p/n 520081-01)
- A2-1.9 Replacing the antenna bracket with a combiner assembly
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- Checklist 1 - Installation Checklist
- Checklist 2 - Commissioning Checklist
Release 3.3, Revision A 1/99
BTS Field Maintenance 109
A2-1.1 Replacing the WAVEXpress/BTS IWP card
This section contains the procedures for replacing the IWP card on a WAVEXpress/BTS. Refer to Figure A2-1
"WAVEXpress/BTS field replaceable units" on page 108 for an illustration of the replacement position.
Step 1
Inform the OMC operator to shutdown the WAVEXpress/BTS using the OMC.
Step 2
Power off the WAVEXpress/BTS by switching the power switch to the OFF position.
Step 3
Ensure that anti-static precautions are taken.
Step 4
Using a Phillips screwdriver, unscrew the two screws located at the top and bottom of the IWP card.
Step 5
Remove the IWP card by firmly pulling the two white tabs located at the top and bottom of the IWP
card.
Step 6
Place the new IWP card into the slot and slide in the card until it completely rests inside the slot. Push
the card firmly into place.
Step 7
Using a Phillips screwdriver, screw in the two removed screws onto the IWP card.
Step 8
Power on the WAVEXpress/BTS by switching the power switch to the ON position.
Step 9
Monitor the bootup process, refer to the maintenance manual for procedures.
BEFORE PERFORMING ANY FIELD REPLACEMENT PROCEDURES,
AN ANTI-STATIC
WRISTBAND MUST BE WORN
. MAKE SURE THAT THE WRISTBAND IS PROPERLY
GROUNDED BEFORE HANDLING THE EQUIPMENT.
WHEN REMOVING THE IWP CARD, POWER TO THE BTS MUST BE SHUTDOWN,
AND SERVICE WILL BE INTERRUPTED
.
!