7-2.1 Post On-Line Commissioning Procedures
Step 1
Leave the power to the BTS on.
Step 2
Check that all T1 and power cable connections to the BTS are tight.
Step 3
Close and lock the BTS door.
Step 4
Ensure that the BTS' site is left in a tidy state.
At this point, the commissioner can leave the BTS’ site.
NOTE
The BCCH can be assigned to any TRX within the BTS. The label “First TRX” applies to
the TRX to which is assigned the BCCH. The OMC operator may determine which
physical TRX is the “1st, 2nd or 3rd”.