On-Line Commissioning
7-1 Introduction
The on-line commissioning of the BTS takes place on-site in conjunction with the OMC operator, after installation and
off-line commissioning. The aim of commissioning is to verify that the WAVEXpress/BTS is operational and can be
integrated into a telecommunications network.
The on-line commissioning process is split into two consecutive steps:
Step 1
Pre-commissioning visual checks, where the field technician verifies that the BTS is still in an appropri-
ate working state for on-line commissioning.
Step 2
On-line commissioning, where the BTS' proper operation is verified via the OMC.
NOTE
The necessary steps for on-line commissioning are summarized in Checklist 2.