Installation Manual
Table Of Contents
- WAVEXpress/BTS Installation and Commissioning Guide
- One - Unpacking the WAVEXpress/BTS
- Two - Internal BTS Cabling and Jumpering
- Three - Installation
- 3-1 Wall Installation
- 3-2 Table Mount
- 3-3 Rack Installation
- 3-4 Common Final Installation Procedures
- 3-4.1 Connection of the Cable Gland
- 3-4.2 Connection of the Grounding Cable
- 3-4.3 Connection of the Antennas to the Bulkhead Plate
- 3-4.4 Connection of the Optional Combiner Assembly
- 3-4.5 Connection of the Power Supply
- 3-4.6 Connection of the T1 Lines
- 3-4.7 Connection to External Alarms
- 3-4.8 Optional Voltage Standing Wave Ratio (VSWR) Check
- 3-4.9 Post Installation Checks
- 3-5 Outdoor Installation
- Four - Off-Line Commissioning
- Five - Off-Line Commissioning of a Daisy Chain
- Six - Post Off-Line Commissioning
- Seven - On-Line Commissioning
- Appendix 1 - Connection of the Combiner Assembly
- Appendix 2 - BTS Field Maintenance
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- A2-1.1 Replacing the WAVEXpress/BTS IWP card
- A2-1.2 Replacing the WAVEXpress/BTS T1 card
- A2-1.3 Replacing the WAVEXpress/BTS TRX card
- A2-1.4 Replacing the WAVEXpress/BTS RF distribution card
- A2-1.5 Replacing the clock module
- A2-1.6 Replacing power supply units
- A2-1.7 Replacing fan assemblies
- A2-1.8 Replacing filters (p/n 520081-01)
- A2-1.9 Replacing the antenna bracket with a combiner assembly
- A2-1 WAVEXpress/BTS Field Replacement Maintenance
- Checklist 1 - Installation Checklist
- Checklist 2 - Commissioning Checklist
Release 3.3, Revision A 1/99
82 WAVEXpress/BTS Installation and Commissioning Guide
Step 4
If the Abis timeslot was changed, the WAVEXpress must be rebooted. Type:
bts
:A->
reboot
5-2 Prerequisites to Daisy Chaining
Step 1
Ensure that all WAVEXpresses comprising the daisy chain are installed and off-line commissioned.
Step 2
Ensure that the Abis Manager timeslot has been set for each WAVEXpress/BTS in the daisy chain as
outlined in Section 10-1. Each BTS within this daisy chain MUST be allocated a different Abis timeslot
number.
Step 3
Turn the power off to all units.
Step 4
Verify that all T1 lines are in place and commissioned by the operator from the BSC to the first BTS,
and between all successive BTS comprising the daisy chain.
NOTE
☛
In the case of daisy chained WAVEXpresses, the Abis timeslot for each unit in the
daisy chain must be set to a different number. For example:
• BTS 1 in the chain = Set timeslot 16 as the Abis timeslot
• BTS 2 in the chain = Set timeslot 17 as the Abis timeslot
• BTS 3 in the chain = Set timeslot 18 as the Abis timeslot
• BTS 4 in the chain = Set timeslot 19 as the Abis timeslot
Make sure that this information is communicated to the OMC operator.
NOTE
☛
For daisy chained WAVEXpresses, the T1 card(s) of the WAVEXpress machine
automatically enters a by-pass mode in the event of a power loss. The card is
equpped with a relay in the signal path which provides continuity between the A-
port and the B-port connector pins. In the event of a power outage, the A-port Rx
signal from a remote destination is presented at the B-port Tx pins; the A-port Tx
signal is driven from the B-port Rx pins by the remote source.