Page 42 InterReach picoBTS Installation Guide
© 2008, ADC Telecommunications, Inc.
ADCP-77-061 • Issue A • 08/2008 • Chapter 4 - On-Line Testing
4.3 POST ON-LINE COMMISSIONING PROCEDURES
1 Leave the power to the OMC-R and picoBTS on.
2 Check that all power cable and ground connections are tight.
3 Ensure that the picoBTS site is left in a tidy state.
This concludes the commissioning of the picoBTS. The technician may now leave the
picoBTS site.