Page 38 InterReach picoBTS Installation Guide
© 2008, ADC Telecommunications, Inc.
ADCP-77-061 • Issue A • 08/2008 • Chapter 4 - On-Line Testing
Figure 4-1: On-Line Commissioning Procedures
Procedures for OMC Operator
AD235811
Procedures for Field
Technician (at picoBSS)
Step 2
Reconnect
WAN Cable
Step 1
Disconnect
WAN Link Cable
Configure Cell
Configure Abis
interface to BSC
Create picoBSS
on OMC or BSC
Verify
Status Changes
Check Alarm
Event Log
Check Alarm
Event Log
Enable Cell
Check State
Verify Test Calls Make Test Calls
Site Clean-up
Step 3
Check LEDs are
Green and Steady
Preliminary