ADCP-77-061 • Issue A • 08/2008 • Chapter 4 - On-Line Testing
4.1 PRE ON-LINE COMMISSIONING REQUIREMENTS
Before on-line commissioning begins, the field technician or the OMC-R operator must verify
that:
The picoBTS, BSC and the MSC are fully commissioned, in service and connected to each
other.
The BSC is in service and connected to the picoBTS.
The OMC-R operator has successfully created and configured the picoBTS object on the
OMC-R and downloaded this information to the picoBTS. Refer to the procedures
described in the FlexWave BSS documentation.
The RF frequencies are cleared to transmit.
The BSC-picoBTS Ethernet link is properly configured and operational.
The HLR subscriber data has been entered into the MSC HLR. In particular, the HLR
must be configured to support the SIM cards of the mobiles used by the field technician.