User's Manual
Table Of Contents
- InterReach picoBTS Installation and Commissioning Guide
- TABLE OF CONTENTS
- Chapter 1 - Unpacking and Configuration Verification
- Chapter 2 - Installation
- Chapter 3 - Commissioning and Configuration
- Chapter 4 - On-Line Testing
InterReach picoBTS Installation Guide Page 23
© 2008, ADC Telecommunications, Inc.
ADCP-77-061 • Issue A • 08/2008 • Chapter 3 - Commissioning and Configuration
3.1 PRE-COMMISSIONING
This section must be completed before doing the commissioning. The commissioning of the
chassis should take place on-site after the physical installation of the picoBTS. Use the appro-
priate lists depending on where the off-line commissioning is being performed.
3.1.1 ON-SITE VISUAL INSPECTION
If you are doing your visual inspection on-site, check that:
• The chassis has been securely installed at the appropriate site.
• The power to the chassis is OFF.
• The chassis is connected to a suitable power source.
• The chassis is correctly grounded.
• All cables are available and secured in their correct positions.
Caution: DO NOT turn the power supply ON until you have a DAS or external antenna connected to
EACH antenna port.
Preliminary