InterReach picoBTS Installation Guide Page 37
© 2008, ADC Telecommunications, Inc.
ADCP-77-061 • Issue A • 08/2008 • Chapter 4 - On-Line Testing
4.2 ON-LINE COMMISSIONING
The network commissioning procedures must be performed using the OMC-R and with in the
coverage area provided by the picoBTS. This requires one or two persons working from at
least two different documentation sets:
• A field technician who is on-site within the coverage area of picoBTS and DAS system.
They must have a copy of this manual and the appropriate DAS documentation.
• An OMC-R operator who uses the FlexWave OMC-R or BSC Configuration Manager to
configure and enable the picoBTS in the network. They must have the appropriate
FlexWave documention for the procedures they are perfoming.
The flowchart shown in Figure 4-1 provides a high-level view of the procedures. The proce-
dures in the following sections provide detailed, numbered steps.
Note: Before starting any of the following procedures, the field technician needs to ensure that
anti-static precautions are taken. Refer to
Section 1.2.
Preliminary