InterReach picoBTS Installation Guide Page 9
© 2008, ADC Telecommunications, Inc.
ADCP-77-061 • Issue A • 08/2008 • Chapter 2 - Installation
2.2 MOUNTING THE PICOBTS CHASSIS
The picoBTS chassis is shipped with the appropriate hardware to be installed in a 19” rack.
This section describes all the necessary steps for installing a picoBTS.
2.2.1 REQUIRED MATERIALS
• 4 standard 19” (48.26 cm) rack mount screws (customer-provided)
2.2.1.1 Optional Materials
• Cable ties
2.2.1.2 Required Tools
• Phillips screwdriver
2.2.2 RACK MOUNT ADVISORY
To prevent bodily injury when mounting or servicing this unit in a rack, you must take special
precautions to ensure that the system remains stable. The following guidelines are provided to
ensure your safety:
• This unit should be mounted at the bottom of the rack if it is the only unit in the rack.
• When mounting this unit in a partially filled rack, load the rack from the bottom to the top
with the heaviest component at the bottom of the rack.
• If the rack is provided with stabilizing devices, install the stabilizers before mounting or
servicing the unit in the rack.
Attention: Pour éviter toute blessure corporelle pendant les opérations de montage ou de répa-
ration de cette unité en casier, il convient de prendre des précautions spéciales afin de
Note: Ensure that:
• The ambient temperature around the unit (which may be higher than the room temperature) is within
the limit specified for the unit.
• There is sufficient airflow around the unit.
• The electrical circuits are not overloaded - consider the name plate rating of all the connected
equipment and make sure you have over current protection.
• The 19” equipment rack is properly grounded.
CAUTION:
Preliminary