Page 68 FlexWave microBTS Installation and Commissioning Guide
© 2009, ADC Telecommunications, Inc.
ADCP-77-086 • Issue 2 • 04/2009 • Chapter 5 - microBTS Initial Configuration
5.8 Verifying BTS Functionality Using the BSC Configuration Manager
To verify the installed BTS is functioning, use the following procedure:
1 Right click on the new site shown on the BSC Configuration Manager “tree” and a dialog
box will appear. Select Unlock.
The BTS will now begin transmitting on the AFRCN number selected in the previous
steps. This can be verified at the site by means of an external power meter and frequency
counter or a spectrum analyzer if available.
Make a phone call by working in conjunction with the system administrator.
Note: Further information regarding the configuration of the microBTS TRX units can be
found in the instructions set forth in ADC publication ADCP-75-310