User Manual
Table Of Contents
- FlexWave microBTS 1 x 1 and 2 x 1 Installation and Commissioning Guide
- Chapter 1 - Introduction
- Chapter 2 - Unpacking and Inspection
- Chapter 3 - Mounting Procedures
- Chapter 4 - Installation Procedures
- 4.1 Installation Overview
- 4.1.1 Installation Hardware Provided with microBTS Enclosure
- 4.1.2 Tools and Materials Required
- 4.1.3 Ground Wire Installation
- 4.1.4 Network Listen Antenna Installation
- 4.1.5 IP Backhaul Cable Installation
- 4.1.6 Base Station Antenna Cable Installation
- 4.1.7 AC Power Wiring Installation
- 4.1.8 DC Power Wiring Installation
- 4.1.9 Touch-Up Painting
- 4.1.10 Shield Installation (option)
- 4.2 microBTS Replacement
- 4.1 Installation Overview
- Chapter 5 - microBTS Initial Configuration
FlexWave microBTS Installation and Commissioning Guide Page 47
© 2009, ADC Telecommunications, Inc.
ADCP-77-086 • Issue 2 • 04/2009 • Chapter 5 - microBTS Initial Configuration
12 Verify that the MAC address for the microBTS matches the information provided in the
list shown in Figure 5-5. Verify these MAC addresses match the equipment label shown in
Figure 5-7.
The TRX’s on the label will be listed first. The last address will be the microBTS terminal.
This address will be used to access the web browser when setting a static IP address.
Record these numbers for future reference.
Figure 5-6: The Configure BTS Screen Used to Set the DHCP Server Address
AD090901