User Manual
Table Of Contents
- FlexWave microBTS 1 x 1 and 2 x 1 Installation and Commissioning Guide
- Chapter 1 - Introduction
- Chapter 2 - Unpacking and Inspection
- Chapter 3 - Mounting Procedures
- Chapter 4 - Installation Procedures
- 4.1 Installation Overview
- 4.1.1 Installation Hardware Provided with microBTS Enclosure
- 4.1.2 Tools and Materials Required
- 4.1.3 Ground Wire Installation
- 4.1.4 Network Listen Antenna Installation
- 4.1.5 IP Backhaul Cable Installation
- 4.1.6 Base Station Antenna Cable Installation
- 4.1.7 AC Power Wiring Installation
- 4.1.8 DC Power Wiring Installation
- 4.1.9 Touch-Up Painting
- 4.1.10 Shield Installation (option)
- 4.2 microBTS Replacement
- 4.1 Installation Overview
- Chapter 5 - microBTS Initial Configuration
Page 42 FlexWave microBTS Installation and Commissioning Guide
© 2009, ADC Telecommunications, Inc.
ADCP-77-086 • Issue 2 • 04/2009 • Chapter 5 - microBTS Initial Configuration
5.2 Configuring the Equipment for IP Connection
5.2.1 Introduction
In order to initialize, test, and operate the microBTS it must be connected to an IP network. By
connecting the microBTS, Router, and PC to the IP network as shown in the following proce-
dure, the microBTS can be provisioned with a static or DHCP IP address and can be
configured for correct operation using the BTS Installer and BSC Configuration Manager
Utilities.
1 Connect the microBTS, PC, four port Ethernet router/switch and, RF termination (if no
antenna system is installed) as shown in Figure 5-1.
Figure 5-1: Connection Details for Initialization of the microBTS Terminal
FlexWave microBTS
Ethernet Router, Hub
or Switch
RJ-48 Ethernet
Patch cable
AD015901