User Manual
Table Of Contents
- FlexWave microBTS 1 x 1 and 2 x 1 Installation and Commissioning Guide
- Chapter 1 - Introduction
- Chapter 2 - Unpacking and Inspection
- Chapter 3 - Mounting Procedures
- Chapter 4 - Installation Procedures
- 4.1 Installation Overview
- 4.1.1 Installation Hardware Provided with microBTS Enclosure
- 4.1.2 Tools and Materials Required
- 4.1.3 Ground Wire Installation
- 4.1.4 Network Listen Antenna Installation
- 4.1.5 IP Backhaul Cable Installation
- 4.1.6 Base Station Antenna Cable Installation
- 4.1.7 AC Power Wiring Installation
- 4.1.8 DC Power Wiring Installation
- 4.1.9 Touch-Up Painting
- 4.1.10 Shield Installation (option)
- 4.2 microBTS Replacement
- 4.1 Installation Overview
- Chapter 5 - microBTS Initial Configuration
FlexWave microBTS Installation and Commissioning Guide Page 35
© 2009, ADC Telecommunications, Inc.
ADCP-77-086 • Issue 2 • 04/2009 • Chapter 4 - Installation Procedures
Use the following procedure to install the DC power wiring:
1 Locate the DC power cable that is provided separately with the enclosure.
2 Route the power cable between the DC power port, located on the underside of the enclo-
sure and the DC power supply as shown in Figure 4-8. It may be necessary to install a new
junction box for the 5 amp breaker if an existing junction box is not available.
Note: All electrical work must comply with local codes and requirements. A locally licensed electri-
cal contractor is best qualified to perform this work. For additional information, consult with the ADC
Customer Service.
DANGER: Use extreme caution when working with DC power. Ensure all power is disconnected
before working on power circuits.