User Manual
Table Of Contents
- FlexWave microBTS 1 x 1 and 2 x 1 Installation and Commissioning Guide
- Chapter 1 - Introduction
- Chapter 2 - Unpacking and Inspection
- Chapter 3 - Mounting Procedures
- Chapter 4 - Installation Procedures
- 4.1 Installation Overview
- 4.1.1 Installation Hardware Provided with microBTS Enclosure
- 4.1.2 Tools and Materials Required
- 4.1.3 Ground Wire Installation
- 4.1.4 Network Listen Antenna Installation
- 4.1.5 IP Backhaul Cable Installation
- 4.1.6 Base Station Antenna Cable Installation
- 4.1.7 AC Power Wiring Installation
- 4.1.8 DC Power Wiring Installation
- 4.1.9 Touch-Up Painting
- 4.1.10 Shield Installation (option)
- 4.2 microBTS Replacement
- 4.1 Installation Overview
- Chapter 5 - microBTS Initial Configuration
Page 14 FlexWave microBTS Installation and Commissioning Guide
© 2009, ADC Telecommunications, Inc.
ADCP-77-086 • Issue 2 • 04/2009 • Chapter 3 - Mounting Procedures
3.1 Before Mounting the microBTS
3.1.1 Introduction
This section provides instructions for mounting the FlexWave microBTS. The microBTS may
be secured to an interior or exterior wall, attached to a utility pole, or attached to a horizontal
cable (strand-mount). Mounting the microBTS from a cable requires an accessory kit not
included with the unit. Read this section in its entirety prior to installing the microBTS.
3.1.2 Mounting Considerations
Before mounting the microBTS, verify that the installation site is in conformance with the
system design plan (not documented here). If a system design plan has not been prepared,
consult the ADC Customer Service for technical assistance. The site chosen must conform to
all local codes and any permits required must be obtained prior to the start of mounting. The
location must be accessible and provide adequate parking for worker and vehicle safety. The
installed unit must not create a visual or physical obstruction to vehicular or pedestrian traffic
or block pole-climbing access.
The microBTS must be located as specified in the system design plan and must have ready
access to the specified AC or DC power source. The site must provide adequate ventilation and
must comply with the unit environmental specifications. A minimum of 18 inches of clearance
must be provided on all sides (except the back) of the enclosure to allow free air circulation. In
addition, the bottom (cable entry end) and either the top, the front, or one of the sides must be
open to free air space. Adequate clearance must be allowed at the bottom of the enclosure to
provide access for attaching cables and for viewing the LED indicator.
3.1.3 Mounting Hardware Provided With the microBTS
The microBTS is shipped with the mounting hardware required for a typical wall-mount or
pole-mount installation. Table 3-1 lists the mounting hardware provided. Additional hardware
may have to be provided by the installer depending on the site requirements.
E
Note: The microBTS is intended for restricted access locations only.
Table 3-1: microBTS Mounting Hardware and Fasteners
Item Quantity
Hoisting ring assembly 1
Hoisting ring assembly mounting screws 2
Mounting bracket 1
Strapping 2