User Manual
Table Of Contents
- FlexWave microBTS 1 x 1 and 2 x 1 Installation and Commissioning Guide
- Chapter 1 - Introduction
- Chapter 2 - Unpacking and Inspection
- Chapter 3 - Mounting Procedures
- Chapter 4 - Installation Procedures
- 4.1 Installation Overview
- 4.1.1 Installation Hardware Provided with microBTS Enclosure
- 4.1.2 Tools and Materials Required
- 4.1.3 Ground Wire Installation
- 4.1.4 Network Listen Antenna Installation
- 4.1.5 IP Backhaul Cable Installation
- 4.1.6 Base Station Antenna Cable Installation
- 4.1.7 AC Power Wiring Installation
- 4.1.8 DC Power Wiring Installation
- 4.1.9 Touch-Up Painting
- 4.1.10 Shield Installation (option)
- 4.2 microBTS Replacement
- 4.1 Installation Overview
- Chapter 5 - microBTS Initial Configuration
Page 12 FlexWave microBTS Installation and Commissioning Guide
© 2009, ADC Telecommunications, Inc.
ADCP-77-086 • Issue 2 • 04/2009 • Chapter 2 - Unpacking and Inspection
2.1 Unpacking and Inspecting the microBTS
This section provides instructions for opening the shipping boxes, verifying that all parts have
been received, and verifying that no shipping damage has occurred. The basic microBTS
includes the following items:
• microBTS enclosure
• Network Listen antenna
• Fasteners, cables, strapping, and mounting bracket as specified in Table 3-1, Section 3,
and Table 4-1, Section 4.
The following accessories may also be shipped with the microBTS:
• Strand mount kit (optional item)
• Lightning protector (optional item)
• Solar shields (optional item)
Use the following procedure to unpack and inspect the microBTS components:
1 Open the shipping cartons and carefully unpack each component from the protective
packing material.
2 Check each component for broken or missing parts. If there are damages, contact ADC
(see the last page in this document) for an RMA (Return Material Authorization) and to
reorder if replacement is required.