User's Manual

Table Of Contents
Preparing for System Installation
InterReach Fusion Wideband Installation, Operation, and Reference Manual Page 111
D-620616-0-20 Rev K TECP-77-044 Issue 9 March 2015 © 2015 TE Connectivity
PREPARING FOR SYSTEM INSTALLATION
Pre-Installation Inspection
Follow this procedure before installing Fusion Wideband equipment.
1 Verify the number of packages received against the packing list.
2 Check all packages for external damage; re
port any external damage to the shipping carrier.
If there is damage, a shipping agent should be present before you unpack and inspect the
contents because damage caused during transit is the responsibility of the shipping agent.
3 Open and check each package against the pack
ing list. If any items are missing, contact TE
customer service (see Appendix D: Contacting TE Connectivity” on page 229).
4 If dama
ge is discovered at the time of in
stallation, contact the shipping agent.
Installation Checklist
Table 89. Installation Checklist
Installation Requirement Consideration
Floor Plans Installation location of equipme
nt clearly marked
System Design Used to verify frequency bands af
ter installation
Power available:
Fusion Wideband Main Hub (AC)
Fusion Wideband Expansion Hub (AC)
To RAU (DC)
Fusion Wideband Main Hub (DC)
Fusion Wideband Expansion Hub (DC)
Hub’s power cord is 2 m (6.5 ft) long.
115/230V, 2/1A, 50–60 Hz
115/230V, 6/3A, 50-60 Hz
54V (from the Hub)
38–64VDC, 2.5A
38–64VDC, 14A
Rack space available
(Main and Expansion Hub)
89 mm (3.5 in.) high (2U)
Wall-Mount Fusion Wideband Main Hub Hub must be mounted on 3/4-inch plywood backboard.
Clearance for air circulation:
Fusion Wideband Main or Expansion Hub
RAU
76 mm (3 in.) front and rear, 51 mm (2 in.) sides
76 mm (3 in.) all around
Suitable operating environment:
Fusion Wideband Main or Expansion Hub
Indoor location only
0° to +45°C (+32° to +113°F)
5% to 95% non-condensing humidity
RAUs –25° to +45°C (–13° to +113°F)