User Manual
Help Hot Line (U.S. only): 1-800-530-9960 7-13
D-620616-0-20 Rev G CONFIDENTIAL
Fusion Wideband Installation Procedures
• The rack-mounting brackets on the Fusion Wideband Main Hub must be moved to
the recessed mounting position (shown in Figure 7-2) to allow for the required 76
mm (3 in.) rear clearance.
• The maximum weight the bracket can hold is 22.5 kg (50 lbs).
• The bracket is designed to accommodate a Fusion Wideband Main Hub (12 lbs.) or
an Expansion Hub (14.5 lbs.).
• The wall mount bracket should be securely mounted to wall, using the four key slot
mounting holes on the bracket.
Using the Wall Rack-Mounting Option
You can flip the rack mounting brackets, as shown in Figure 7-2, so the hub can be
mounted 76 mm (3 in.) forward in the rack.
Figure 7-2 Bracket Detail For Wall Mount Rack (PN 4712)
To install the Hub to the wall-mounted rack:
1. Attach the wall bracket (PN 4712) to wall the using #10 Pan Head wood screws,
1-1/2” minimum length for mounting in wood studs or 3/4“thick plywood.
The bracket must be positioned so that the Hub will be in a horizontal position
when it is installed. (Refer to Figure 7-2.)
NOTE: If wall stud spacing of 16” is not available, TE recommends that
3/4” plywood be pre-installed to the wall. You can then attach the bracket to
the plywood using the wood screws.
2. Remove both of the rack mounting brackets from the Hub.