User's Manual
Installing the LGCell
9-4 LGCell 4.0 Installation, Operation, and Reference Manual PN 8100-40
620004-0 Rev. B
9.2.2 Tools and Materials Required to Install Main Hub
The tools and materials required to install the Main Hub are listed in the following
table.
Distances
Main Hub is within 3–6m
(10–20 ft) of connecting
repeater
If longer distance, determine the loss of the cable used for this connection and adjust
the RF signal into the Main Hub accordingly. This can be done by readjusting the
power from the base station, or by changing the attenuation value between the base
station/repeater and the Main Hub.
Main Hub is within 3–6m
(10–20 ft) of connecting base
station
Main Hub is within 1 km (3300 ft) of Expansion Hub(s); 3 dB optical link budget
Miscellaneous
Cable manager Rack space immediately above or below the Main Hub; 8.9 cm (3.5 in.) high
Description
Philips screwdriver
Mounting screws and spring nuts
Power cord
Fiber cleaning supplies (optical grade alcohol and lint-free wipes)
Compressed air (optical grade)
Installation Requirement Consideration