User's Manual Part 1

Managing and Planning an LGCell Project
6-2 LGCell 4.0 Installation, Operation, and Reference Manual PN 8100-40
620004-0 Rev. E
6.1 Managing an LGCell Project
Proper project management is instrumental in providing timely and accurate deploy-
ment of the LGCell system. It is beneficial to have one person manage and coordinate
all aspects of the project: planning, designing, and installing the equipment. The
project manager is the person responsible for assigning tasks and ensuring scheduled
work is performed on time. The project manager also acts as the coordinator between
all the people involved in the project.
The following table shows an estimated timeline for project management.
Table 6-1 Project Management Estimated Timeline
Description Details Time Interval
Detailed site
walk-through/RF survey
Prepare installation information, including RF plan, floor plan, equipment
order form, and final design documents.
1 to 2 weeks
Order LGCell equipment Get all parts and accessories required. 8 weeks*
*Standard delivery after receipt of order.
Select cabling contractor Complete installation statement of work and provide floor plan with equip-
ment locations, cabling runs, and other materials and connections. Get
cabling quotation after walk-through.
2 weeks
Install cable Monitor installation. 1 to 5 days
Install LGCell Review installation checklist and prepare all materials.
Refer to Section 6.3 on page 6-8.
1 to 3 days
Test installation and RF
coverage
Be sure there are no uncovered areas.
Refer to Section 6.4 on page 6-9.
1 hour per RAU
Generate as-built document Prepare site plan diagram and coverage performance. 1 to 5 days