User's Manual
Table Of Contents
- UltraWAVE BTS 6 Installation and Commissioning Guide
- One - Unpacking and Configuration Verification
- Two - Installation
- 2-1 Site Requirements
- 2-2 Mounting the BTS Chassis
- 2-3 Configuring the E1 or T1 Trunk Card
- 2-4 Connecting Power and Ground Cables
- 2-5 Connecting E1 or T1 Trunk Cables
- 2-6 Connecting Antennas
- 2-6.1 Omni 1 TRX (O1) Configuration
- 2-6.2 Omni 2 TRX (O2) Configuration
- 2-6.3 Omni 3 TRX (O3) Configuration
- 2-6.4 Omni 4 TRX (O4) Configuration
- 2-6.5 Omni 5 TRX (O5) Configuration
- 2-6.6 Omni 6 TRX (O6) Configuration
- 2-6.7 Omni 5 (05) and Omni 6 (O6) 25 Watt Configuration
- 2-6.8 Sectorized Two TRX (S11) Configuration
- 2-6.9 Sectorized Three TRX (S111) Configuration
- 2-6.10 Two Sector Four TRX (S22) Configuration
- 2-6.11 Three Sector Four TRX (S211) Configuration
- 2-6.12 Three Sector Five TRX (S221) Configuration
- 2-6.13 Three Sector Six TRX (S222) Configuration
- 2-6.14 Two Sector Five TRX (S32) Configuration
- 2-6.15 Two Sector Six TRX (S33) Configuration
- 2-6.16 Two Sector Six TRX (S42) Configuration
- 2-6.17 RF Radiation Hazard
- 2-7 Connecting External Alarms
- 2-8 Post Installation Cabling and Checks
- Three - Off-Line Commissioning
- 3-1 Pre Off-Line Commissioning
- 3-2 Off-Line Commissioning the UltraWAVE BTS
- 3-3 Software verification using Craft PC
- 3-3.1 Verifying the Current Software Version and Patch Level
- 3-3.2 Checking the Flash Version Number
- 3-3.3 Running E1 or T1 POST Diagnostics
- 3-3.4 Verifying Telnet Communications with the BTS over Ethernet
- 3-3.5 Running TRX POST Diagnostics
- 3-3.6 Reviewing POST Results
- 3-3.7 Rebooting the BTS after Running POST
- 3-3.8 Terminating Serial Communications with the BTS
- 3-4 Exiting XWindows on the Craft PC
- 3-5 Upgrading the BTS Software Version (Flash)
- 3-6 Post Off-Line Commissioning
- Four - Off-Line Commissioning of a Daisy Chain
- Five - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
On-Line Commissioning 75
Before disconnecting the E1 or T1 cables, the field technician must make sure that the cable is labeled
in a way that clearly identifies its origin (a particular E1 or T1 port of the BSC, or a particular port of an E1
or T1 panel, etc.) and destination (a particular E1 or T1 slot and port on the BSC).
• Provide the OMC operator with all part, revision and serial numbers for the BTS cards and
modules. This information was gathered during the physical installation and is available in
Checklist 1.
Recovery Tests
1 At the installation site, power off the BTS. Have the OMC operator verify the changed state
of the BTS.
2 At the installation site, power on the BTS. Have the OMC operator verify the changed state of
the BTS.
3 Have the OMC operator lock the E1 or T1 ports, and verify that BTS alarms appear.
4 Have the OMC operator unlock the E1 or T1 ports, and verify that BTS alarms clear.
5 At the BTS, disconnect all E1 and/or T1 cables. Monitor the LED sequence of the BTS as
described in Chapter Three.
6 Reconnect both E1 and/or T1 cables to the BTS E1 or T1 trunk card. Monitor the LED
sequence of the BTS as described in Chapter Three.
External Alarm Tests
1 Test external alarms as per the following procedures:
Test 1
A Open the door of the BTS.
B After a delay, the OMC operator must observe an alarm event.
C Close the door.
D After a delay, the alarm state displayed at the OMC changes from open to closed.
Test 2
A If the first external alarm is used, close the alarm relay (i.e. trigger the first
customer-defined alarm).
B After a delay, the OMC operator must observe an alarm event.
C Close the alarm relay by opening the alarm contact.
D After a delay, the alarm state displayed at the OMC changes from open to closed.
Before starting any of the following procedures, the field technician
needs to ensure that anti-static precautions are taken.