68 UltraWAVE BTS Installation and Commissioning Guide, Release 6.5A
3-6 Post Off-Line Commissioning
The following post off-line commissioning procedures are necessary to ensure that the BTS is ready for
on-line commissioning. In the case of off-line commissioning at a staging area, these procedures ensure
that the BTS is ready for installation. In the case of off-line commissioning after on-site installation, these
procedures ensure that the BTS is ready for on-line commissioning.
Post Off-Line Commissioning Procedures at the Staging Area
1 Repack the BTS in its original shipping containers and make sure that it is shipped to the site
where it will be installed.
2 Once the BTS is installed at its final site as described in Chapter Two, continue with the next
section.
Post Off-Line Commissioning Procedures On-Site
1 Reconnect the E1 or T1 cables to the digital distribution frame.
2 Power on the BTS if it is not already on. Verify that all PWR and ON LINE LEDs are green.
3 Inform the OMC operator that the BTS is ready for network configuration.
4 After the OMC operator has configured the BTS, continue with on-line commissioning tests
in the next chapter.