User's Manual
Table Of Contents
- UltraWAVE BTS 6 Installation and Commissioning Guide
- One - Unpacking and Configuration Verification
- Two - Installation
- 2-1 Site Requirements
- 2-2 Mounting the BTS Chassis
- 2-3 Configuring the E1 or T1 Trunk Card
- 2-4 Connecting Power and Ground Cables
- 2-5 Connecting E1 or T1 Trunk Cables
- 2-6 Connecting Antennas
- 2-6.1 Omni 1 TRX (O1) Configuration
- 2-6.2 Omni 2 TRX (O2) Configuration
- 2-6.3 Omni 3 TRX (O3) Configuration
- 2-6.4 Omni 4 TRX (O4) Configuration
- 2-6.5 Omni 5 TRX (O5) Configuration
- 2-6.6 Omni 6 TRX (O6) Configuration
- 2-6.7 Omni 5 (05) and Omni 6 (O6) 25 Watt Configuration
- 2-6.8 Sectorized Two TRX (S11) Configuration
- 2-6.9 Sectorized Three TRX (S111) Configuration
- 2-6.10 Two Sector Four TRX (S22) Configuration
- 2-6.11 Three Sector Four TRX (S211) Configuration
- 2-6.12 Three Sector Five TRX (S221) Configuration
- 2-6.13 Three Sector Six TRX (S222) Configuration
- 2-6.14 Two Sector Five TRX (S32) Configuration
- 2-6.15 Two Sector Six TRX (S33) Configuration
- 2-6.16 Two Sector Six TRX (S42) Configuration
- 2-6.17 RF Radiation Hazard
- 2-7 Connecting External Alarms
- 2-8 Post Installation Cabling and Checks
- Three - Off-Line Commissioning
- 3-1 Pre Off-Line Commissioning
- 3-2 Off-Line Commissioning the UltraWAVE BTS
- 3-3 Software verification using Craft PC
- 3-3.1 Verifying the Current Software Version and Patch Level
- 3-3.2 Checking the Flash Version Number
- 3-3.3 Running E1 or T1 POST Diagnostics
- 3-3.4 Verifying Telnet Communications with the BTS over Ethernet
- 3-3.5 Running TRX POST Diagnostics
- 3-3.6 Reviewing POST Results
- 3-3.7 Rebooting the BTS after Running POST
- 3-3.8 Terminating Serial Communications with the BTS
- 3-4 Exiting XWindows on the Craft PC
- 3-5 Upgrading the BTS Software Version (Flash)
- 3-6 Post Off-Line Commissioning
- Four - Off-Line Commissioning of a Daisy Chain
- Five - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
64 UltraWAVE BTS Installation and Commissioning Guide, Release 6.5A
3-3.7 Rebooting the BTS after Running POST
1 Type:
bts-> reboot [ENTER]
This action places the TRX in an on-line and operational state.
2 Reconnect all E1 or T1 lines to the BTS.
3-3.8 Terminating Serial Communications with the BTS
bts:> postReportE1Trx
******************* E1 DIAGNOSTICS REPORT *******************
*************************************************************
Slot:1
E1(1)TID01: Initialize Peripheral Registers : PASS
E1(1)TID02: Peripheral Register Test : PASS
E1(1)TID03: Framer Register Test : PASS
E1(1)TID04: VME to CPU FIFO Flag Test : PASS
E1(1)TID05:Initialize Time/Space sw Chip : PASS
E1(1)TID06: Software Download Test : Not-Run
E1(1)TID07: Memory Test : Not-Run
E1(1)TID08: CPM download Test : Not-Run
E1(1)TID09: TRAU DSP Test : Not-Run
E1(1)TID10: Cross Connect Test : Not-Run
*************************************************************
******************* TRX DIAGNOSTICS REPORT ******************
*************************************************************
Slot 6
-------------------------------------------------------------
All Tests PASSED
*************************************************************
value=58=0x3a='="
bts:>
Figure 3-10 Reviewing E1 or T1 and TRX POST Results
There are five tests that are not run but show up in the results section
when the user manually retrieves the POST results. These tests are not
displayed when running POST by rebooting the BTS. They are:
• T1(1) TID06: Software Download Test : Not-Run
• T1(1) TID07: Memory Test : Not-Run
• T1(1) TID08: CPM Download Test : Not-Run
• T1(1) TID09: TRAU DSP Test: Not-Run
• T1(1) TID10: Cross Connect Test: Not-Run
If you are going to perform the Racal tests described in the interWAVE
Radio Test Manual at this time, ensure that you have rebooted the
chassis. Also, leave the Craft PC connected to the IWP card and a serial
communications session active.