User's Manual
Table Of Contents
- UltraWAVE BTS 6 Installation and Commissioning Guide
- One - Unpacking and Configuration Verification
- Two - Installation
- 2-1 Site Requirements
- 2-2 Mounting the BTS Chassis
- 2-3 Configuring the E1 or T1 Trunk Card
- 2-4 Connecting Power and Ground Cables
- 2-5 Connecting E1 or T1 Trunk Cables
- 2-6 Connecting Antennas
- 2-6.1 Omni 1 TRX (O1) Configuration
- 2-6.2 Omni 2 TRX (O2) Configuration
- 2-6.3 Omni 3 TRX (O3) Configuration
- 2-6.4 Omni 4 TRX (O4) Configuration
- 2-6.5 Omni 5 TRX (O5) Configuration
- 2-6.6 Omni 6 TRX (O6) Configuration
- 2-6.7 Omni 5 (05) and Omni 6 (O6) 25 Watt Configuration
- 2-6.8 Sectorized Two TRX (S11) Configuration
- 2-6.9 Sectorized Three TRX (S111) Configuration
- 2-6.10 Two Sector Four TRX (S22) Configuration
- 2-6.11 Three Sector Four TRX (S211) Configuration
- 2-6.12 Three Sector Five TRX (S221) Configuration
- 2-6.13 Three Sector Six TRX (S222) Configuration
- 2-6.14 Two Sector Five TRX (S32) Configuration
- 2-6.15 Two Sector Six TRX (S33) Configuration
- 2-6.16 Two Sector Six TRX (S42) Configuration
- 2-6.17 RF Radiation Hazard
- 2-7 Connecting External Alarms
- 2-8 Post Installation Cabling and Checks
- Three - Off-Line Commissioning
- 3-1 Pre Off-Line Commissioning
- 3-2 Off-Line Commissioning the UltraWAVE BTS
- 3-3 Software verification using Craft PC
- 3-3.1 Verifying the Current Software Version and Patch Level
- 3-3.2 Checking the Flash Version Number
- 3-3.3 Running E1 or T1 POST Diagnostics
- 3-3.4 Verifying Telnet Communications with the BTS over Ethernet
- 3-3.5 Running TRX POST Diagnostics
- 3-3.6 Reviewing POST Results
- 3-3.7 Rebooting the BTS after Running POST
- 3-3.8 Terminating Serial Communications with the BTS
- 3-4 Exiting XWindows on the Craft PC
- 3-5 Upgrading the BTS Software Version (Flash)
- 3-6 Post Off-Line Commissioning
- Four - Off-Line Commissioning of a Daisy Chain
- Five - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
Off-Line Commissioning 63
3-3.6 Reviewing POST Results
This section explains how to review E1 or T1 POST and TRX POST diagnostics results after POST has
been completed on the BTS.
1 To display the most current E1 or T1 and TRX POST results after POST has been completed,
type:
bts-> postReportE1Trx [ENTER]
A summary of the E1 or T1 and TRX POST results will be displayed (note that some tests
may not run):
397.933 (Diag) TRX CARD IN SLOT 6: STARTING TRX POST OFFLINE Test
399.083 (Diag ) IRP(6) tf 5 Test VME Access....................... PASSED
400.783 (Diag ) IRP(6) tf 12 Load FPGA (TDM) ....................... PASSED
401.116 (Diag ) IRP(6) tf 15 Load FPGA (TXTDMA) .................... PASSED
401.449 (Diag ) IRP(6) tf 14 Load FPGA (RXTDMA) .................... PASSED
404.383 (Diag ) IRP(6) tf 16 Load DSP (Coder) ...................... PASSED
404.399 (Diag ) IRP(6) tf 19 Ping DSP (Coder) ...................... PASSED
404.433 (Diag ) IRP(6) tf 22 DSP Diag Mode ON (Coder) .............. PASSED
404.949 (Diag ) IRP(6) tf 27 Test External RAM (Coder) ............. PASSED
406.949 (Diag ) IRP(6) tf 17 Load DSP (Equalizer) .................. PASSED
406.966 (Diag ) IRP(6) tf 20 Ping DSP (Equalizer) .................. PASSED
407.000 (Diag ) IRP(6) tf 24 DSP Diag Mode ON (Equalizer) .......... PASSED
407.516 (Diag ) IRP(6) tf 28 Test External RAM (Equalizer) ......... PASSED
408.549 (Diag ) IRP(6) tf 6 Test DSP to VME Interrupt ............. PASSED
409.883 (Diag ) IRP(6) tf 30 Test TDM Control Store RAM ............ PASSED
414.116 (Diag ) IRP(6) tf 34 Test TDM Loop-back .................... PASSED
414.349 (Diag ) IRP(6) tf 45 Test ADC .............................. PASSED
415.149 (Diag ) IRP(6) tf 35 Test RXTDMA to Equalizer Serial Bus ... PASSED
415.199 (Diag ) IRP(6) tf 38 Test Coder to TXTDMA Serial Bus ....... PASSED
415.299 (Diag ) IRP(6) tf 40 Test Equalizer To Coder Serial Bus .... PASSED
430.199 (Diag ) IRP(6) tf 41 Test Channel Synthesizers ............. PASSED
433.049 (Diag ) IRP(6) tf 42 Test Local Oscillator ................. PASSED
433.083 (Diag ) IRP(6) tf 23 DSP Diag Mode OFF (Coder) ............. PASSED
433.116 (Diag ) IRP(6) tf 25 DSP Diag Mode OFF (Equalizer) ......... PASSED
433.116 (Diag ) IRP CARD IN SLOT 6 : COMPLETED POST OFFLINE Test : PASSED
***Starting up SP1
***Starting up SP0
Figure 3-9 GPRS Enabled TRX POST Results
The following procedure assumes that E1 or T1 and TRX POST have just
been completed on the selected BTS and a serial connection is still
active between the Craft PC and the BTS. If this is not the case, reboot
the BTS and run POST again.