User's Manual
Table Of Contents
- UltraWAVE BTS 6 Installation and Commissioning Guide
- One - Unpacking and Configuration Verification
- Two - Installation
- 2-1 Site Requirements
- 2-2 Mounting the BTS Chassis
- 2-3 Configuring the E1 or T1 Trunk Card
- 2-4 Connecting Power and Ground Cables
- 2-5 Connecting E1 or T1 Trunk Cables
- 2-6 Connecting Antennas
- 2-6.1 Omni 1 TRX (O1) Configuration
- 2-6.2 Omni 2 TRX (O2) Configuration
- 2-6.3 Omni 3 TRX (O3) Configuration
- 2-6.4 Omni 4 TRX (O4) Configuration
- 2-6.5 Omni 5 TRX (O5) Configuration
- 2-6.6 Omni 6 TRX (O6) Configuration
- 2-6.7 Omni 5 (05) and Omni 6 (O6) 25 Watt Configuration
- 2-6.8 Sectorized Two TRX (S11) Configuration
- 2-6.9 Sectorized Three TRX (S111) Configuration
- 2-6.10 Two Sector Four TRX (S22) Configuration
- 2-6.11 Three Sector Four TRX (S211) Configuration
- 2-6.12 Three Sector Five TRX (S221) Configuration
- 2-6.13 Three Sector Six TRX (S222) Configuration
- 2-6.14 Two Sector Five TRX (S32) Configuration
- 2-6.15 Two Sector Six TRX (S33) Configuration
- 2-6.16 Two Sector Six TRX (S42) Configuration
- 2-6.17 RF Radiation Hazard
- 2-7 Connecting External Alarms
- 2-8 Post Installation Cabling and Checks
- Three - Off-Line Commissioning
- 3-1 Pre Off-Line Commissioning
- 3-2 Off-Line Commissioning the UltraWAVE BTS
- 3-3 Software verification using Craft PC
- 3-3.1 Verifying the Current Software Version and Patch Level
- 3-3.2 Checking the Flash Version Number
- 3-3.3 Running E1 or T1 POST Diagnostics
- 3-3.4 Verifying Telnet Communications with the BTS over Ethernet
- 3-3.5 Running TRX POST Diagnostics
- 3-3.6 Reviewing POST Results
- 3-3.7 Rebooting the BTS after Running POST
- 3-3.8 Terminating Serial Communications with the BTS
- 3-4 Exiting XWindows on the Craft PC
- 3-5 Upgrading the BTS Software Version (Flash)
- 3-6 Post Off-Line Commissioning
- Four - Off-Line Commissioning of a Daisy Chain
- Five - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
56 UltraWAVE BTS Installation and Commissioning Guide, Release 6.5A
1 If not already done, connect the Craft PC to the BTS as described in Section 3-2.1, and start
XWindows on the Craft PC as described in Section 3-2.2.
2 If an Xterm window does not launch, left click your mouse button and choose Xterm.
3 In an Xterm window, type:
build@craftpc:~> cu -l ttyS0 [ENTER]
Where l is lower case L and 0 is zero.
4 After the returned message
Connected appears, press the [ENTER] key. The prompt
now changes to the following:
bts->
3-2.5 Verifying/Changing Boot Parameters
In this section, you verify the boot parameters and change them if necessary. There are three reasons to
change boot parameters:
• If they are configured incorrectly, you must set them to the values shown here.
• If your system is connected to the Ethernet, you must set the IP address to support the
Craft PC IP address 172.16.80.43. To make a connection with the Craft PC, set the
processor card IP address to 172.16.80.42:fffff000.
• The TARGET NAME sets the IP name, and provides text for the prompt. Contact your
network administrator if you are unsure what value to enter. The default is “iwbox”.
After changing the boot parameters, the BTS must be rebooted before the changes take effect.
1 If not already done, establish serial communications with the BTS as described in
Section 3-2.4. If the BTS starts rebooting endlessly, refer to the interWAVE Craft PC Guide
for corrective measures. If the BTS boots normally, type:
bts-> bootChange [ENTER]
2 A list of boot parameters appears. Use the following commands to edit the parameter values:
For more information about the Craft PC, refer to the interWAVE Craft
PC Guide.
The following section describes procedures performed using the Craft
PC. For more information about the Craft PC, please to the interWAVE
Craft PC Guide.