User's Manual
Table Of Contents
- UltraWAVE BTS 6 Installation and Commissioning Guide
- One - Unpacking and Configuration Verification
- Two - Installation
- 2-1 Site Requirements
- 2-2 Mounting the BTS Chassis
- 2-3 Configuring the E1 or T1 Trunk Card
- 2-4 Connecting Power and Ground Cables
- 2-5 Connecting E1 or T1 Trunk Cables
- 2-6 Connecting Antennas
- 2-6.1 Omni 1 TRX (O1) Configuration
- 2-6.2 Omni 2 TRX (O2) Configuration
- 2-6.3 Omni 3 TRX (O3) Configuration
- 2-6.4 Omni 4 TRX (O4) Configuration
- 2-6.5 Omni 5 TRX (O5) Configuration
- 2-6.6 Omni 6 TRX (O6) Configuration
- 2-6.7 Omni 5 (05) and Omni 6 (O6) 25 Watt Configuration
- 2-6.8 Sectorized Two TRX (S11) Configuration
- 2-6.9 Sectorized Three TRX (S111) Configuration
- 2-6.10 Two Sector Four TRX (S22) Configuration
- 2-6.11 Three Sector Four TRX (S211) Configuration
- 2-6.12 Three Sector Five TRX (S221) Configuration
- 2-6.13 Three Sector Six TRX (S222) Configuration
- 2-6.14 Two Sector Five TRX (S32) Configuration
- 2-6.15 Two Sector Six TRX (S33) Configuration
- 2-6.16 Two Sector Six TRX (S42) Configuration
- 2-6.17 RF Radiation Hazard
- 2-7 Connecting External Alarms
- 2-8 Post Installation Cabling and Checks
- Three - Off-Line Commissioning
- 3-1 Pre Off-Line Commissioning
- 3-2 Off-Line Commissioning the UltraWAVE BTS
- 3-3 Software verification using Craft PC
- 3-3.1 Verifying the Current Software Version and Patch Level
- 3-3.2 Checking the Flash Version Number
- 3-3.3 Running E1 or T1 POST Diagnostics
- 3-3.4 Verifying Telnet Communications with the BTS over Ethernet
- 3-3.5 Running TRX POST Diagnostics
- 3-3.6 Reviewing POST Results
- 3-3.7 Rebooting the BTS after Running POST
- 3-3.8 Terminating Serial Communications with the BTS
- 3-4 Exiting XWindows on the Craft PC
- 3-5 Upgrading the BTS Software Version (Flash)
- 3-6 Post Off-Line Commissioning
- Four - Off-Line Commissioning of a Daisy Chain
- Five - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
Off-Line Commissioning 51
Setting Up a Serial Connection via the ICP Processor Card Serial Port
1 Connect the RJ-11 patch cable to ICP processor card connector labeled ‘CON’.
2 Connect the opposite end of the patch cable to the RJ-11 to DB9 adapter and connect the
DB9 adapter to the serial port on the back of the Craft PC, as shown in the following figure.
The following figure shows a physical serial port connection between the Craft PC and the ICP
processor card:
Setting Up an Ethernet Connection via the ICP Processor Card Ethernet Port
1 Connect the Ethernet crossover cable to the ICP processor card Ethernet port labeled
“ENET”.
2 Connect the other end of the cable to the Ethernet transceiver.
3 Insert the transceiver firmly into the PCMCIA card slot on the side of the Craft PC.
Figure 3-2 Connecting to the Craft PC via the ICP Serial Port
IW085202
ON/LINE
PORT 1
12
PORT 0
12
ALARMS
FLT
PWR
ALARMS
Craft PC
computer
Serial Port
RJ-11 Patch Cable
RJ-11 to DB-9
Adapter
IIIIIIIIIIIIIIIIIIIIIIIII
P/N XXXXXX
ONLINE
PWR
FLT
SCN
RST
CON
ENET
IIIIIIIIIIIIIIIIIIIIIIIII
S/N XXXXXX