48 UltraWAVE BTS Installation and Commissioning Guide, Release 6.5A
3-1 Pre Off-Line Commissioning
The following sections must be completed before doing the off-line commissioning. The off-line
commissioning of the BTS must take place on-site after installation. It is critical that all RF connections
have been completed before proceeding with the off-line commissioning.
3-1.1 Visual Inspection
Complete the following inspections to ensure that the system is ready for off-line commissioning:
On-Site Visual Inspection
If you are doing your visual inspection on-site, check that:
The cabinet has been securely installed at the appropriate site.
The cabinet power supplies to the cabinet are OFF.
The cabinet is connected to a suitable power source.
The cabinet is correctly grounded.
All cables are available and secured in their correct positions.
All cards and modules are correctly seated and populated according to the original purchase
order.
E1 or T1 transmission cables are available and labeled.
RF transmission cables are connected to antennas.
Compliance and Power Checks
Cross-check with the site specific data to ensure that the BTS is correctly configured with all
cards and modules.
Ensure that you have access to Checklist 2 and that all serial numbers of all cards are listed
there. This should have been completed in Chapter One.
Verify that any test equipment to be used has a current calibration certificate.
The BSS software used in the BTS is highly complex. Before
proceeding,
contact Customer Service to verify that you have the latest
available software. You must
have the correct software CD-ROM and
know the current patch level for your software version before
commissioning the BTS. Contact your Level 2 support representative for
additional assistance.
The off-line commissioning steps are listed in Checklist 3.