User's Manual
Table Of Contents
- UltraWAVE BTS 6 Installation and Commissioning Guide
- One - Unpacking and Configuration Verification
- Two - Installation
- 2-1 Site Requirements
- 2-2 Mounting the BTS Chassis
- 2-3 Configuring the E1 or T1 Trunk Card
- 2-4 Connecting Power and Ground Cables
- 2-5 Connecting E1 or T1 Trunk Cables
- 2-6 Connecting Antennas
- 2-6.1 Omni 1 TRX (O1) Configuration
- 2-6.2 Omni 2 TRX (O2) Configuration
- 2-6.3 Omni 3 TRX (O3) Configuration
- 2-6.4 Omni 4 TRX (O4) Configuration
- 2-6.5 Omni 5 TRX (O5) Configuration
- 2-6.6 Omni 6 TRX (O6) Configuration
- 2-6.7 Omni 5 (05) and Omni 6 (O6) 25 Watt Configuration
- 2-6.8 Sectorized Two TRX (S11) Configuration
- 2-6.9 Sectorized Three TRX (S111) Configuration
- 2-6.10 Two Sector Four TRX (S22) Configuration
- 2-6.11 Three Sector Four TRX (S211) Configuration
- 2-6.12 Three Sector Five TRX (S221) Configuration
- 2-6.13 Three Sector Six TRX (S222) Configuration
- 2-6.14 Two Sector Five TRX (S32) Configuration
- 2-6.15 Two Sector Six TRX (S33) Configuration
- 2-6.16 Two Sector Six TRX (S42) Configuration
- 2-6.17 RF Radiation Hazard
- 2-7 Connecting External Alarms
- 2-8 Post Installation Cabling and Checks
- Three - Off-Line Commissioning
- 3-1 Pre Off-Line Commissioning
- 3-2 Off-Line Commissioning the UltraWAVE BTS
- 3-3 Software verification using Craft PC
- 3-3.1 Verifying the Current Software Version and Patch Level
- 3-3.2 Checking the Flash Version Number
- 3-3.3 Running E1 or T1 POST Diagnostics
- 3-3.4 Verifying Telnet Communications with the BTS over Ethernet
- 3-3.5 Running TRX POST Diagnostics
- 3-3.6 Reviewing POST Results
- 3-3.7 Rebooting the BTS after Running POST
- 3-3.8 Terminating Serial Communications with the BTS
- 3-4 Exiting XWindows on the Craft PC
- 3-5 Upgrading the BTS Software Version (Flash)
- 3-6 Post Off-Line Commissioning
- Four - Off-Line Commissioning of a Daisy Chain
- Five - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
48 UltraWAVE BTS Installation and Commissioning Guide, Release 6.5A
3-1 Pre Off-Line Commissioning
The following sections must be completed before doing the off-line commissioning. The off-line
commissioning of the BTS must take place on-site after installation. It is critical that all RF connections
have been completed before proceeding with the off-line commissioning.
3-1.1 Visual Inspection
Complete the following inspections to ensure that the system is ready for off-line commissioning:
On-Site Visual Inspection
If you are doing your visual inspection on-site, check that:
• The cabinet has been securely installed at the appropriate site.
• The cabinet power supplies to the cabinet are OFF.
• The cabinet is connected to a suitable power source.
• The cabinet is correctly grounded.
• All cables are available and secured in their correct positions.
• All cards and modules are correctly seated and populated according to the original purchase
order.
• E1 or T1 transmission cables are available and labeled.
• RF transmission cables are connected to antennas.
Compliance and Power Checks
• Cross-check with the site specific data to ensure that the BTS is correctly configured with all
cards and modules.
• Ensure that you have access to Checklist 2 and that all serial numbers of all cards are listed
there. This should have been completed in Chapter One.
• Verify that any test equipment to be used has a current calibration certificate.
The BSS software used in the BTS is highly complex. Before
proceeding,
contact Customer Service to verify that you have the latest
available software. You must
have the correct software CD-ROM and
know the current patch level for your software version before
commissioning the BTS. Contact your Level 2 support representative for
additional assistance.
The off-line commissioning steps are listed in Checklist 3.