User's Manual
Table Of Contents
- UltraWAVE BTS 6 Installation and Commissioning Guide
- One - Unpacking and Configuration Verification
- Two - Installation
- 2-1 Site Requirements
- 2-2 Mounting the BTS Chassis
- 2-3 Configuring the E1 or T1 Trunk Card
- 2-4 Connecting Power and Ground Cables
- 2-5 Connecting E1 or T1 Trunk Cables
- 2-6 Connecting Antennas
- 2-6.1 Omni 1 TRX (O1) Configuration
- 2-6.2 Omni 2 TRX (O2) Configuration
- 2-6.3 Omni 3 TRX (O3) Configuration
- 2-6.4 Omni 4 TRX (O4) Configuration
- 2-6.5 Omni 5 TRX (O5) Configuration
- 2-6.6 Omni 6 TRX (O6) Configuration
- 2-6.7 Omni 5 (05) and Omni 6 (O6) 25 Watt Configuration
- 2-6.8 Sectorized Two TRX (S11) Configuration
- 2-6.9 Sectorized Three TRX (S111) Configuration
- 2-6.10 Two Sector Four TRX (S22) Configuration
- 2-6.11 Three Sector Four TRX (S211) Configuration
- 2-6.12 Three Sector Five TRX (S221) Configuration
- 2-6.13 Three Sector Six TRX (S222) Configuration
- 2-6.14 Two Sector Five TRX (S32) Configuration
- 2-6.15 Two Sector Six TRX (S33) Configuration
- 2-6.16 Two Sector Six TRX (S42) Configuration
- 2-6.17 RF Radiation Hazard
- 2-7 Connecting External Alarms
- 2-8 Post Installation Cabling and Checks
- Three - Off-Line Commissioning
- 3-1 Pre Off-Line Commissioning
- 3-2 Off-Line Commissioning the UltraWAVE BTS
- 3-3 Software verification using Craft PC
- 3-3.1 Verifying the Current Software Version and Patch Level
- 3-3.2 Checking the Flash Version Number
- 3-3.3 Running E1 or T1 POST Diagnostics
- 3-3.4 Verifying Telnet Communications with the BTS over Ethernet
- 3-3.5 Running TRX POST Diagnostics
- 3-3.6 Reviewing POST Results
- 3-3.7 Rebooting the BTS after Running POST
- 3-3.8 Terminating Serial Communications with the BTS
- 3-4 Exiting XWindows on the Craft PC
- 3-5 Upgrading the BTS Software Version (Flash)
- 3-6 Post Off-Line Commissioning
- Four - Off-Line Commissioning of a Daisy Chain
- Five - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
40 UltraWAVE BTS Installation and Commissioning Guide, Release 6.5A
2-6.14 Two Sector Five TRX (S32) Configuration
This is a 25 watt (44 dBm) four antenna configuration available in either 850 MHz or 900 MHz
frequencies. This configuration has one sector with three TRXs in one sector and two TRXs in the other
sector.
• Connect your antennas as shown in Figure 2-27.
2-6.15 Two Sector Six TRX (S33) Configuration
This is a 25 watt (44 dBm) four antenna configuration available in either 850 MHz or 900 MHz
frequencies. This configuration has two sectors with three TRXs per sector.
• Connect your antennas as shown in Figure 2-28.
Figure 2-27 Antenna Cabling for S32 Configuration
Figure 2-28 Antenna Cabling for S33 Configuration
ANT ANT
ANT
DIV
ANT
MAIN
RF modules
IW009309
Internal RF connector
External RF connector
Antenna 1
Diversity
Antenna connection
1 2 3 4 50
Not Used Not Used
Antenna 1
Main
Antenna 2
Main
Antenna 2
Diversity
ANT ANTANT ANT
RF modules
IW009310
Internal RF connector
External RF connector
Antenna 1
Diversity
Antenna connection
1 2 3 4 50
Not Used Not Used
Antenna 1
Main
Antenna 2
Main
Antenna 2
Diversity