User's Manual
Table Of Contents
- UltraWAVE BTS 6 Installation and Commissioning Guide
- One - Unpacking and Configuration Verification
- Two - Installation
- 2-1 Site Requirements
- 2-2 Mounting the BTS Chassis
- 2-3 Configuring the E1 or T1 Trunk Card
- 2-4 Connecting Power and Ground Cables
- 2-5 Connecting E1 or T1 Trunk Cables
- 2-6 Connecting Antennas
- 2-6.1 Omni 1 TRX (O1) Configuration
- 2-6.2 Omni 2 TRX (O2) Configuration
- 2-6.3 Omni 3 TRX (O3) Configuration
- 2-6.4 Omni 4 TRX (O4) Configuration
- 2-6.5 Omni 5 TRX (O5) Configuration
- 2-6.6 Omni 6 TRX (O6) Configuration
- 2-6.7 Omni 5 (05) and Omni 6 (O6) 25 Watt Configuration
- 2-6.8 Sectorized Two TRX (S11) Configuration
- 2-6.9 Sectorized Three TRX (S111) Configuration
- 2-6.10 Two Sector Four TRX (S22) Configuration
- 2-6.11 Three Sector Four TRX (S211) Configuration
- 2-6.12 Three Sector Five TRX (S221) Configuration
- 2-6.13 Three Sector Six TRX (S222) Configuration
- 2-6.14 Two Sector Five TRX (S32) Configuration
- 2-6.15 Two Sector Six TRX (S33) Configuration
- 2-6.16 Two Sector Six TRX (S42) Configuration
- 2-6.17 RF Radiation Hazard
- 2-7 Connecting External Alarms
- 2-8 Post Installation Cabling and Checks
- Three - Off-Line Commissioning
- 3-1 Pre Off-Line Commissioning
- 3-2 Off-Line Commissioning the UltraWAVE BTS
- 3-3 Software verification using Craft PC
- 3-3.1 Verifying the Current Software Version and Patch Level
- 3-3.2 Checking the Flash Version Number
- 3-3.3 Running E1 or T1 POST Diagnostics
- 3-3.4 Verifying Telnet Communications with the BTS over Ethernet
- 3-3.5 Running TRX POST Diagnostics
- 3-3.6 Reviewing POST Results
- 3-3.7 Rebooting the BTS after Running POST
- 3-3.8 Terminating Serial Communications with the BTS
- 3-4 Exiting XWindows on the Craft PC
- 3-5 Upgrading the BTS Software Version (Flash)
- 3-6 Post Off-Line Commissioning
- Four - Off-Line Commissioning of a Daisy Chain
- Five - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
10 UltraWAVE BTS Installation and Commissioning Guide, Release 6.5A
5 For each TRX card, write down the part number, revision number and serial number in the
installation checklist.
6 Verify that all empty slots have blank panels covering them.
7 Check the shipping invoice and verify that the system has the correct number of power
modules (2 or 3). If the third power module is not installed, verify that the slot is covered by
a blank panel.
8 For each power module, write down the part number, revision number and serial number in
the installation checklist.
9 Verify that the clock module is installed. Write down its part number, revision number and
serial number in the installation checklist.
10 Verify all empty slots are covered by blank panels. These are necessary for cooling and to
meet RF emission standards.
1-4 Internal Cabling Overview
Cabling inside the BTS cabinet is routed to connectors accessible on the outside of the cabinet
assembly. The internal cabling connects the E1 or T1 card to the external interface cable plate interface.
Antenna connections are also routed internally to provide an N-type connector on the top of the
cabinet.
The internal cabling of the BTS depends on the configuration ordered by the customer. It is completed
by the manufacturer. Due to its complexity, it is not recommended for you to move or disconnect
internal cabling. Schematics of the internal RF cabling are provided in Appendix 1.
Proceed to Chapter Two to install your BTS.
67
Note: Systems equipped with less than six TRXs will have blank panels
covering the empty slots.
Extreme care should be used when working around SMA cables, as
misalignment or loosening of the cable with the connectors can
damage both parts and degrade the cable's performance.
Table 1-3 TRX Slot Assignments
TRX Card # Slots