Commissioning Checklist 89
4 __ OMC downloaded BTS configuration with correct operational parameters.
5 __ RF frequencies cleared to transmit.
6 __ BTS E1 or T1 trunk card cables connected to the local telephone provider demarcation.
7 __ BSC E1 or T1 trunk card cables connected to the local telephone provider demarcation assigned to
the BTS.
Note: It is the operator’s responsibility to verify all E1 and/or T1 links are properly
installed and certified by local telephone provider facilities. Certification must rate
Length of Testing and BER Results.
BTS-BSC Network Integration
1 __ Unlock the Abis interface.
2 __ Unlock the BTS.
3 __ Verify the operational state of the BTS.
Verifying Recovery
1 __ Perform a BTS cold start and verify that the BTS fully recovers.
2 __ Confirm Abis interface re-establishes communications to BSC after E1 or T1 disconnects.
Operational Tests
1 __ Unlock TRX.
2 __ Perform test calls on each timeslot.
3 __ Perform test calls on each TRX.
Final Commissioning, On-Line Tests
1 __ Leave power to BTS on.
2 __ Inform the OMC operator that commissioning is complete.