User's Manual
Table Of Contents
- UltraWAVE BTS 6 Installation and Commissioning Guide
- One - Unpacking and Configuration Verification
- Two - Installation
- 2-1 Site Requirements
- 2-2 Mounting the BTS Chassis
- 2-3 Configuring the E1 or T1 Trunk Card
- 2-4 Connecting Power and Ground Cables
- 2-5 Connecting E1 or T1 Trunk Cables
- 2-6 Connecting Antennas
- 2-6.1 Omni 1 TRX (O1) Configuration
- 2-6.2 Omni 2 TRX (O2) Configuration
- 2-6.3 Omni 3 TRX (O3) Configuration
- 2-6.4 Omni 4 TRX (O4) Configuration
- 2-6.5 Omni 5 TRX (O5) Configuration
- 2-6.6 Omni 6 TRX (O6) Configuration
- 2-6.7 Omni 5 (05) and Omni 6 (O6) 25 Watt Configuration
- 2-6.8 Sectorized Two TRX (S11) Configuration
- 2-6.9 Sectorized Three TRX (S111) Configuration
- 2-6.10 Two Sector Four TRX (S22) Configuration
- 2-6.11 Three Sector Four TRX (S211) Configuration
- 2-6.12 Three Sector Five TRX (S221) Configuration
- 2-6.13 Three Sector Six TRX (S222) Configuration
- 2-6.14 Two Sector Five TRX (S32) Configuration
- 2-6.15 Two Sector Six TRX (S33) Configuration
- 2-6.16 Two Sector Six TRX (S42) Configuration
- 2-6.17 RF Radiation Hazard
- 2-7 Connecting External Alarms
- 2-8 Post Installation Cabling and Checks
- Three - Off-Line Commissioning
- 3-1 Pre Off-Line Commissioning
- 3-2 Off-Line Commissioning the UltraWAVE BTS
- 3-3 Software verification using Craft PC
- 3-3.1 Verifying the Current Software Version and Patch Level
- 3-3.2 Checking the Flash Version Number
- 3-3.3 Running E1 or T1 POST Diagnostics
- 3-3.4 Verifying Telnet Communications with the BTS over Ethernet
- 3-3.5 Running TRX POST Diagnostics
- 3-3.6 Reviewing POST Results
- 3-3.7 Rebooting the BTS after Running POST
- 3-3.8 Terminating Serial Communications with the BTS
- 3-4 Exiting XWindows on the Craft PC
- 3-5 Upgrading the BTS Software Version (Flash)
- 3-6 Post Off-Line Commissioning
- Four - Off-Line Commissioning of a Daisy Chain
- Five - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
88 UltraWAVE BTS Installation and Commissioning Guide, Release 6.5A
BTS Off-Line Software Checks
1 __ Connect the Craft PC to the BTS using a serial and ethernet cable.
2 __ Establish a serial connection.
3 __ Check BTS boot parameters.
4 __ Check the flash version number.
POST Tests
1 __ Verify E1 or T1 POST tests successfully passed.
2 __ Verify TRX POST tests successfully passed for each card.
TRX Commissioning
1 __ Connect the BTS to the Craft PC and the Racal testset.
2 __ Start the Racal.
3 __ Load the sequence files on to the PCMCIA card from the CD-ROM.
4 __ Setup the test results presentation on the Racal.
5 __ Set the offset values for RF cable loss.
6 __ Run the automated test sequence:
___ TRX 1 Pass ____ Fail ___
___ TRX 2 Pass Fail ___
___ TRX 3 Pass Fail ___
___ TRX 3 Pass Fail ___
___ TRX 3 Pass Fail ___
___ TRX 3 Pass Fail ___
Post Racal Procedures
1 __ Disconnect the BTS from the Racal testset.
2 __ Reboot the BTS using the Craft PC.
3 __ Disconnect the BTS from the Craft PC.
Post Off-Line Commissioning
At the Depot
1 __
Physically install BTS on-site
2 __ Connect E1 and/or T1 lines to telephone provider demarcation point.
3 __ Leave power to BTS on.
4 __ Inform OMC operator that BTS is ready for on-line commissioning.
On-Site
1 __
Connect E1 and/or T1 lines to telephone provider demarcation point.
2 __ Leave power to BTS on.
3 __ Inform OMC operator that BTS is ready for on-line commissioning.
On-Line Commissioning
BTS On-Line Commissioning Prerequisites
1 __ BSC in service and connected to BTS.
2 __ OMC in service and connected to BSC.
3 __ Database questionnaire completed with BTS parameters defined.