User's Manual

Table Of Contents
88 UltraWAVE BTS Installation and Commissioning Guide, Release 6.5A
BTS Off-Line Software Checks
1 __ Connect the Craft PC to the BTS using a serial and ethernet cable.
2 __ Establish a serial connection.
3 __ Check BTS boot parameters.
4 __ Check the flash version number.
POST Tests
1 __ Verify E1 or T1 POST tests successfully passed.
2 __ Verify TRX POST tests successfully passed for each card.
TRX Commissioning
1 __ Connect the BTS to the Craft PC and the Racal testset.
2 __ Start the Racal.
3 __ Load the sequence files on to the PCMCIA card from the CD-ROM.
4 __ Setup the test results presentation on the Racal.
5 __ Set the offset values for RF cable loss.
6 __ Run the automated test sequence:
___ TRX 1 Pass ____ Fail ___
___ TRX 2 Pass Fail ___
___ TRX 3 Pass Fail ___
___ TRX 3 Pass Fail ___
___ TRX 3 Pass Fail ___
___ TRX 3 Pass Fail ___
Post Racal Procedures
1 __ Disconnect the BTS from the Racal testset.
2 __ Reboot the BTS using the Craft PC.
3 __ Disconnect the BTS from the Craft PC.
Post Off-Line Commissioning
At the Depot
1 __
Physically install BTS on-site
2 __ Connect E1 and/or T1 lines to telephone provider demarcation point.
3 __ Leave power to BTS on.
4 __ Inform OMC operator that BTS is ready for on-line commissioning.
On-Site
1 __
Connect E1 and/or T1 lines to telephone provider demarcation point.
2 __ Leave power to BTS on.
3 __ Inform OMC operator that BTS is ready for on-line commissioning.
On-Line Commissioning
BTS On-Line Commissioning Prerequisites
1 __ BSC in service and connected to BTS.
2 __ OMC in service and connected to BSC.
3 __ Database questionnaire completed with BTS parameters defined.