UltraWAVE Micro BTS Installation and Commissioning Guide, Version B 69
Pre Off-Line Commissioning
3.1 Pre Off-Line Commissioning
The following sections must be completed before doing the off-line commissioning.
The off-line commissioning of the Micro BTS must take place on-site after
installation. It is critical that all RF connections have been completed before
proceeding with the off-line commissioning.
3.1.1 Visual Inspections
Complete the following inspections to ensure that the system is ready for off-line
commissioning.
On-Site Visual Inspection
If you are doing your visual inspection on-site, check that:
The chassis has been securely installed at the appropriate site.
The chassis power supplies are OFF.
The chassis is connected to a suitable power source.
Power supply fans are running and INPUT LEDs are illuminated.
The chassis is correctly grounded.
All cables are available and secured in their correct positions.
All cards and modules are correctly seated and populated according to the
original purchase order.
E1 or T1 transmission cables are available and labeled.
RF transmission cables are connected to antennas.
Compliance and Power Checks
Cross-check with the site specific data to ensure that the Micro BTS is
correctly configured with all cards and modules.
Ensure that you have access to Checklist 2 - Installation Checklist and that all
serial numbers of all cards are listed there. This should have been completed
in Chapter 1 - Unpacking and Configuration Verification.
Verify that any test equipment to be used has a current calibration certificate.
Verify that the voltage for the installation site match those of the chassis
power supply modules (either 230 VAC, 110 VAC, or -48 VDC, as specified on
the front panel).