Chapter 3 - Off-Line Commissioning
In this Chapter:
“Pre Off-Line Commissioning” on page 69
“Off-Line Commissioning of the Micro BTS” on page 71
“Software Verification using Craft PC” on page 83
“Upgrading the Micro BTS Software Version (Flash)” on page 90
“Post Off-Line Commissioning” on page 92
The off-line commissioning process includes the following steps:
Pre off-line commissioning, where you ensure that the system is in an appro-
priate state. This includes:
Visual inspection
Compliance checks
Startup verification, where you verify that the system boots up correctly by
observing the LEDs on the front panel.
Craft PC tests, where you use the Craft PC to verify the software configuration
and run tests.
Post off-line commissioning, where you prepare the system for on-line
commissioning.
The rest of this chapter includes detailed instructions for these steps.