User's Manual
Table Of Contents
- UltraWAVE Micro BTS Installation and Commissioning Guide
- Chapter 1 - Unpacking and Configuration Verification
- Chapter 2 - Installation
- 2.1 Analyzing Site Requirements
- 2.2 Mounting the Micro BTS Chassis
- 2.3 Configuring the E1 or T1 Trunk Card
- 2.4 Connecting Ground Cables
- 2.5 Connecting Power Supplies
- 2.6 Connecting E1 or T1 Trunk Cables
- 2.7 Connecting Antennas
- 2.8 Connecting External Alarms
- 2.9 Making a Serial Connection to the Processor Card
- 2.10 Network Connections
- 2.11 Post Installation Cabling and Checks
- Chapter 3 - Off-Line Commissioning
- 3.1 Pre Off-Line Commissioning
- 3.2 Off-Line Commissioning of the Micro BTS
- 3.2.1 Starting XWindows Using the Craft PC
- 3.2.2 Connecting the Craft PC to the ICP Processor Card
- 3.2.3 Setting Up a Serial Connection via the ICP Processor Card Serial Port
- 3.2.4 Power-On LED Tests
- 3.2.5 Configuring Boot Parameters
- 3.2.6 Setting Up an Ethernet Connection to the ICP Processor Card Ethernet Port
- 3.2.7 Verifying Telnet Communications with the Micro BTS over Ethernet
- 3.3 Software Verification using Craft PC
- 3.3.1 Verifying the Current Software Version and Patch Level
- 3.3.2 Checking the Flash Version Number
- 3.3.3 Running E1 or T1 POST Diagnostics
- 3.3.4 Running TRX POST Diagnostics
- 3.3.5 Reviewing POST Results
- 3.3.6 Rebooting the Micro BTS after Running POST
- 3.3.7 Terminating Serial Communications with the Micro BTS
- 3.3.8 Exiting XWindows on the Craft PC
- 3.4 Upgrading the Micro BTS Software Version (Flash)
- 3.5 Post Off-Line Commissioning
- Chapter 4 - Off-Line Commissioning of a Daisy Chain
- Chapter 5 - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
- Index
66 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Chapter 2 - Installation
2.11 Post Installation Cabling and Checks
You should ensure that all internal and external cabling is correctly connected.
2.11.1 Connecting the Chassis
Before commissioning the equipment, ensure that:
The Abis interface E1 and/or T1 cables are routed to the telephone provider.
The DIP switch settings on the E1 or T1 trunk cards are set correctly and if
you are using the 75 Ohm E1 trunk card that the ground jumper is in the
correct position. Refer to Section 2.3 for E1 and/or T1 DIP switch settings.
The chassis power is turned off.
Antenna cables are connected to RF antenna port connectors as appropriate.
2.11.2 Verifying External Cabling
It is the operator's responsibility to verify that all inter-chassis E1 and/or T1
links are ordered, installed and certified by the telephone provider according to
ANSI T1.403 specifications before on-line commissioning is performed.
The operator should also perform end-to-end bit error ratio or Bit Error Rate
(BER) tests over a 20-minute period on the E1 and T1 Abis interface link(s),
and verify that the BER is 10
-8
or better.