User's Manual
Table Of Contents
- UltraWAVE Micro BTS Installation and Commissioning Guide
- Chapter 1 - Unpacking and Configuration Verification
- Chapter 2 - Installation
- 2.1 Analyzing Site Requirements
- 2.2 Mounting the Micro BTS Chassis
- 2.3 Configuring the E1 or T1 Trunk Card
- 2.4 Connecting Ground Cables
- 2.5 Connecting Power Supplies
- 2.6 Connecting E1 or T1 Trunk Cables
- 2.7 Connecting Antennas
- 2.8 Connecting External Alarms
- 2.9 Making a Serial Connection to the Processor Card
- 2.10 Network Connections
- 2.11 Post Installation Cabling and Checks
- Chapter 3 - Off-Line Commissioning
- 3.1 Pre Off-Line Commissioning
- 3.2 Off-Line Commissioning of the Micro BTS
- 3.2.1 Starting XWindows Using the Craft PC
- 3.2.2 Connecting the Craft PC to the ICP Processor Card
- 3.2.3 Setting Up a Serial Connection via the ICP Processor Card Serial Port
- 3.2.4 Power-On LED Tests
- 3.2.5 Configuring Boot Parameters
- 3.2.6 Setting Up an Ethernet Connection to the ICP Processor Card Ethernet Port
- 3.2.7 Verifying Telnet Communications with the Micro BTS over Ethernet
- 3.3 Software Verification using Craft PC
- 3.3.1 Verifying the Current Software Version and Patch Level
- 3.3.2 Checking the Flash Version Number
- 3.3.3 Running E1 or T1 POST Diagnostics
- 3.3.4 Running TRX POST Diagnostics
- 3.3.5 Reviewing POST Results
- 3.3.6 Rebooting the Micro BTS after Running POST
- 3.3.7 Terminating Serial Communications with the Micro BTS
- 3.3.8 Exiting XWindows on the Craft PC
- 3.4 Upgrading the Micro BTS Software Version (Flash)
- 3.5 Post Off-Line Commissioning
- Chapter 4 - Off-Line Commissioning of a Daisy Chain
- Chapter 5 - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
- Index
38 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Chapter 2 - Installation
2.5 Connecting Power Supplies
In this section, you will connect the Micro BTS to your power source. Before
beginning it is necessary to first:
Identify your power configuration. This may be AC (110 V to 220 V, 30 A
50-60 Hz) or DC (-40 V to -60 V, 40 A).
Install your AC or DC power supplies.
When you have completed these tasks, refer to the appropriate subsection to
make either AC or DC power connections:
Connecting AC power. See Section 2.5.1
Connecting DC power. See Section 2.5.2
Identifying AC and DC Power Configurations
You can determine whether your system uses AC or DC power by checking the
main configuration label. The main configuration label is located on either the
exterior of your shipping container or on the rear of the Micro subrack assembly.
See Section 1.3.1 for the details included on the main configuration label. Use
Table 1-1 to identify your system power configuration.
Warning: This product relies on the building's installation for
short-circuit (over current) protection. Ensure that a fuse or
circuit breaker no larger than 110 VAC, 30 A; 220 VAC, 15 A; or
-48 VDC, 40 A is used on the phase conductors (all
current-carrying conductors).
Attention: Pour ce qui est de la protection contre les
courts-circuits (surtension), ce produit dépend de l'installation
électrique du local. Vérifier qu'un fusible ou qu'un disjoncteur de
110 VAC, 30 A alt., 220 VAC, 15 A alt., -48 VDC 40 A est utilisé
sur les conducteurs de phase (conducteurs de charge).
Warnung: Dieses Produkt ist darauf angewiesen, daß im
Gebäude ein Kurzschluß- bzw. Überstromschutz installiert ist.
Stellen Sie sicher, daß eine Sicherung oder ein Unterbrecher von
nicht mehr als 110 V Wechselstrom, 30 A; 220 V Wechselstrom,
15 A; oder -48 V Gleichstrom, 40 A an den Phasenleitern (allen
stromführenden Leitern) verwendet wird.