User's Manual
Table Of Contents
- UltraWAVE Micro BTS Installation and Commissioning Guide
- Chapter 1 - Unpacking and Configuration Verification
- Chapter 2 - Installation
- 2.1 Analyzing Site Requirements
- 2.2 Mounting the Micro BTS Chassis
- 2.3 Configuring the E1 or T1 Trunk Card
- 2.4 Connecting Ground Cables
- 2.5 Connecting Power Supplies
- 2.6 Connecting E1 or T1 Trunk Cables
- 2.7 Connecting Antennas
- 2.8 Connecting External Alarms
- 2.9 Making a Serial Connection to the Processor Card
- 2.10 Network Connections
- 2.11 Post Installation Cabling and Checks
- Chapter 3 - Off-Line Commissioning
- 3.1 Pre Off-Line Commissioning
- 3.2 Off-Line Commissioning of the Micro BTS
- 3.2.1 Starting XWindows Using the Craft PC
- 3.2.2 Connecting the Craft PC to the ICP Processor Card
- 3.2.3 Setting Up a Serial Connection via the ICP Processor Card Serial Port
- 3.2.4 Power-On LED Tests
- 3.2.5 Configuring Boot Parameters
- 3.2.6 Setting Up an Ethernet Connection to the ICP Processor Card Ethernet Port
- 3.2.7 Verifying Telnet Communications with the Micro BTS over Ethernet
- 3.3 Software Verification using Craft PC
- 3.3.1 Verifying the Current Software Version and Patch Level
- 3.3.2 Checking the Flash Version Number
- 3.3.3 Running E1 or T1 POST Diagnostics
- 3.3.4 Running TRX POST Diagnostics
- 3.3.5 Reviewing POST Results
- 3.3.6 Rebooting the Micro BTS after Running POST
- 3.3.7 Terminating Serial Communications with the Micro BTS
- 3.3.8 Exiting XWindows on the Craft PC
- 3.4 Upgrading the Micro BTS Software Version (Flash)
- 3.5 Post Off-Line Commissioning
- Chapter 4 - Off-Line Commissioning of a Daisy Chain
- Chapter 5 - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
- Index
UltraWAVE Micro BTS Installation and Commissioning Guide, Version B 27
Mounting the Micro BTS Chassis
2.2.2 Enclosure Mounting
The Micro BTS chassis should be mounted on a concrete pad of sufficient density
to support the weight of the cabinet assembly. Alignment pins may be installed in
the concrete pad at the locations provided in Figure 2-4. The alignment pins
should be 0.5 inches (1.27 cm) in diameter and protrude from 4.1 inches to
4.4 inches (10.41 cm to 11.18 cm) from the concrete pad.
Enough clearance should be provided from the front and back of the cabinet to
fully open the doors. This requires at least 24 inches (61 cm) from the front and
rear doors. The minimum clearance required on either side of the cabinet is
4.5 inches (11.4 cm) and the minimum clearance required below the cabinet is
1.8 inches (4.59 cm). The mounting site should also have ample clearance for the
trunk and antenna cables to be attached to the connectors at the top of the
cabinet.
The required footprint for your cabinet installation must be at least 73.5 inches
(186.7 cm) by 31.5 inches (80 cm). Be sure there is sufficient airflow around the
unit.
Figure 2-4: Cabinet Footprint
Rubber feet
Mounting hole
M16-2 x4 places
20.898 in. [53.08 cm]
22.63 in. [57.48 cm]
Alignment holes
0.551 in. [1.40 cm]
10.00 in.
[25.40 cm]
14.567 in.
[37.00] cm
IW021301