User's Manual

Table Of Contents
18 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Chapter 2 - Installation
2.1 Analyzing Site Requirements
Before a site is chosen or equipment installed, a site survey must be carried out.
The site survey checklist assists the surveyor with the inspection and the
collection of site specific information such as environmental conditions, electrical
requirements, and mechanical requirements.
The site survey checklist must be completed before installation begins. The
necessary steps for site readiness are listed in Checklist 1 - Site Readiness
Checklist. The GSM Network Implementation Manual
provides additional detailed
site requirements.
The site readiness checklist assists the field service engineer or operator to ensure
that the site is ready for equipment installation. It includes information about:
Environmental conditions
Electrical requirements
Chassis requirements
The site readiness checklist is located in Checklist 1 - Site Readiness Checklist. It
must be completed as part of the installation process.
2.1.1 Environmental Conditions
The Micro BTS is designed to operate indoors only. To facilitate long-term
operability and durability of the Micro BTS, observe specific environmental
constraints.
Before installing the Micro BTS, ensure that the operating environment maintains
a temperature and humidity within the ranges shown in Table 2-1.
Make sure the ambient temperature around the unit (which may
be higher than the room temperature) is within the specified limit
for the unit.
Table 2-1: Micro BTS Operating Environment
Scale
Humidity
(non-condensing)
Temperature
(Celsius)
Temperature
(Fahrenheit)
Maximum 90% 55 degrees 131 degrees
Minimum 10% -5 degrees 23 degrees