User's Manual
Table Of Contents
- UltraWAVE Micro BTS Installation and Commissioning Guide
- Chapter 1 - Unpacking and Configuration Verification
- Chapter 2 - Installation
- 2.1 Analyzing Site Requirements
- 2.2 Mounting the Micro BTS Chassis
- 2.3 Configuring the E1 or T1 Trunk Card
- 2.4 Connecting Ground Cables
- 2.5 Connecting Power Supplies
- 2.6 Connecting E1 or T1 Trunk Cables
- 2.7 Connecting Antennas
- 2.8 Connecting External Alarms
- 2.9 Making a Serial Connection to the Processor Card
- 2.10 Network Connections
- 2.11 Post Installation Cabling and Checks
- Chapter 3 - Off-Line Commissioning
- 3.1 Pre Off-Line Commissioning
- 3.2 Off-Line Commissioning of the Micro BTS
- 3.2.1 Starting XWindows Using the Craft PC
- 3.2.2 Connecting the Craft PC to the ICP Processor Card
- 3.2.3 Setting Up a Serial Connection via the ICP Processor Card Serial Port
- 3.2.4 Power-On LED Tests
- 3.2.5 Configuring Boot Parameters
- 3.2.6 Setting Up an Ethernet Connection to the ICP Processor Card Ethernet Port
- 3.2.7 Verifying Telnet Communications with the Micro BTS over Ethernet
- 3.3 Software Verification using Craft PC
- 3.3.1 Verifying the Current Software Version and Patch Level
- 3.3.2 Checking the Flash Version Number
- 3.3.3 Running E1 or T1 POST Diagnostics
- 3.3.4 Running TRX POST Diagnostics
- 3.3.5 Reviewing POST Results
- 3.3.6 Rebooting the Micro BTS after Running POST
- 3.3.7 Terminating Serial Communications with the Micro BTS
- 3.3.8 Exiting XWindows on the Craft PC
- 3.4 Upgrading the Micro BTS Software Version (Flash)
- 3.5 Post Off-Line Commissioning
- Chapter 4 - Off-Line Commissioning of a Daisy Chain
- Chapter 5 - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
- Index
14 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Chapter 1 - Unpacking and Configuration Verification
1.4.4 Verification Procedure
Use the following procedure to identify and record your system components.
Compare components against those listed in the shipping checklist. See
Figure 1-9 for Micro BTS chassis component locations.
1 Verify that the subrack assembly has four fan assemblies on the power
amplifier side on the rear of the chassis and two fans on the VME bus cards
side on the rear of the chassis. Verify that the fans are securely fastened to the
chassis.
2 Verify that the Micro BTS rack assembly contains an one or more RF modules
in slots A, B and/or C of the Micro rack assembly. Write down the part
number, revision number and serial number of each RF module in Checklist 2
- Installation Checklist.
3 Verify that the chassis contains an ICP processor card in slot 0 of the Micro
subrack assembly. Write down the processor card part number, revision
number and serial number in Checklist 2 - Installation Checklist.
4 Slot 1 of the Micro subrack assembly should contain an E1 or T1 card. From
the shipping checklist, write down the part number, revision number and
serial number of the E1 or T1 card in Checklist 2 - Installation Checklist.
5 Slots 2 to 7 should contain one or more TRXs. Verify how many are required
from the shipping checklist, then verify that they are all there. Write down the
part number, revision number and serial number of each TRX card in Check-
list 2 - Installation Checklist.
6 Check the shipping checklist and verify that the power supply subrack
assembly has one or two power supply modules and power supply fan assem-
blies. One or two power supply modules are required depending on your
configuration. Verify that a third slot and any other open slot is covered with a
blank panel.
For each power supply module, write down the part number, revision number
and serial number in Checklist 2 - Installation Checklist.
7 Verify that all empty slots are covered by blank panels. These are necessary for
cooling, and to meet RF emission standards.