User's Manual
Table Of Contents
- UltraWAVE Micro BTS Installation and Commissioning Guide
- Chapter 1 - Unpacking and Configuration Verification
- Chapter 2 - Installation
- 2.1 Analyzing Site Requirements
- 2.2 Mounting the Micro BTS Chassis
- 2.3 Configuring the E1 or T1 Trunk Card
- 2.4 Connecting Ground Cables
- 2.5 Connecting Power Supplies
- 2.6 Connecting E1 or T1 Trunk Cables
- 2.7 Connecting Antennas
- 2.8 Connecting External Alarms
- 2.9 Making a Serial Connection to the Processor Card
- 2.10 Network Connections
- 2.11 Post Installation Cabling and Checks
- Chapter 3 - Off-Line Commissioning
- 3.1 Pre Off-Line Commissioning
- 3.2 Off-Line Commissioning of the Micro BTS
- 3.2.1 Starting XWindows Using the Craft PC
- 3.2.2 Connecting the Craft PC to the ICP Processor Card
- 3.2.3 Setting Up a Serial Connection via the ICP Processor Card Serial Port
- 3.2.4 Power-On LED Tests
- 3.2.5 Configuring Boot Parameters
- 3.2.6 Setting Up an Ethernet Connection to the ICP Processor Card Ethernet Port
- 3.2.7 Verifying Telnet Communications with the Micro BTS over Ethernet
- 3.3 Software Verification using Craft PC
- 3.3.1 Verifying the Current Software Version and Patch Level
- 3.3.2 Checking the Flash Version Number
- 3.3.3 Running E1 or T1 POST Diagnostics
- 3.3.4 Running TRX POST Diagnostics
- 3.3.5 Reviewing POST Results
- 3.3.6 Rebooting the Micro BTS after Running POST
- 3.3.7 Terminating Serial Communications with the Micro BTS
- 3.3.8 Exiting XWindows on the Craft PC
- 3.4 Upgrading the Micro BTS Software Version (Flash)
- 3.5 Post Off-Line Commissioning
- Chapter 4 - Off-Line Commissioning of a Daisy Chain
- Chapter 5 - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
- Index
2 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Chapter 1 - Unpacking and Configuration Verification
1.1 Unpacking and Inspecting
The UltraWAVE Micro BTS is packed with great care, and all containers are
inspected prior to shipment.
Micro BTS components that are shipped separately include:
Micro subrack assembly
Power supplies
Power supply subrack assembly
The Micro subrack assembly includes RF Module(s), processor card, E1 or T1
card, TRX card(s) and the clock module.
Upon receipt of these packages, immediately inspect the outside of the shipping
containers. If there is any visible damage, insist that a representative of the
carrier is present when unpacking the contents.
Carefully inspect the system as it is unpacked. If any damage, such as dents or
broken connections, is noticeable, immediately notify the carrier as well as
Alvarion Customer Service.
Store the shipping containers for future use. If the unit has to be returned for
upgrade or service, the specially designed shipping containers assure adequate
protection for the equipment. If for some reason the containers are not reusable or
if they are misplaced, please contact Alvarion to order new containers.
1.1.1 Unpacking the Cabinet
The UltraWAVE Micro BTS is shipped in a specially designed carton. The cabinet
should remain in the packaging until shipped to its final destination. Use this
procedure to unpack your cabinet.
1 Move the cabinet to a level, well illuminated area.
2 Cut all of the strapping on the outside of the shipping container. See
Figure 1-1.