Checklist 3 - Commissioning Checklist
Pre-Commissioning Visual Checks
1 __ Installation secure.
2 __ Power to the chassis is off.
3 __ The chassis is connected to a power source.
4 __ The chassis is grounded.
5 __ Equipment cables are labeled and secured.
6 __ Cards are seated securely.
7 __ Transmission cables are available and labeled.
Compliance Checks
1 __ Cross check with site-specific data to ensure the Micro BTS is correctly configured
with all cards.
2 __ Serial number of all cards are recorded.
3 __ Verify correct operating voltage supplied: AC (110 V to 220 V, 30 A, 50-60 Hz) or
DC (-40 V to -60 V, 40 A).
Powering On the Micro BTS
1 __ Disconnect all E1 and/or T1 cables from Micro BTS (if connected).
2 __ Turn power to the chassis on.
3 __ Verify all card power LEDs and processor and on-line LEDs are green.
Table C3-1: Site Details
Site Name
IP Address
IP Name (optional)
MSC Name
Micro BTS Name
Site/Access Phone Number