132 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Checklist 2 - Installation Checklist
Unpacking the Micro BTS
1 __ Check for visible damage to shipping materials. Contact Alvarion Customer Ser-
vice if any visible damage is found.
2 __ All parts included per shipping invoice.
3 __ Cross check with site specific data to ensure Micro BTS is correctly configured
with all cards.
Mounting the Micro BTS on a Rack (if applicable)
1 __ Attach mounting brackets to chassis.
2 __ Mount chassis in rack.
3 __ Ground chassis.
4 __ Connect power supply: 110 VAC to 220 VAC, 30 A, 50-60 Hz or -40 VDC to
-60 VDC, 40 A.
Connecting the Micro BTS
1 __ Connect “A Interface” E1 or T1 trunk cables to local telephone provider demarca-
tion.
2 __ Configure E1 or T1 trunk card DIP switch settings.
3 __ Ensure power to BTS is off.
Verifying the MSC-Micro BTS Link
It is the operator’s responsibility to verify that all MSC-Micro BTS E1 or T1 links
are ordered, installed and certified by the local telephone facilities/operator.
Verify bit error rates on a nominal 20 minute soak test on the E1 or T1 A-interface
(end-to-end BER test to include E1or T1 trunk cables). The Micro BTS is now
ready for commissioning tests.
Table C2-3: Power Supply Subrack Equipment
Power Supply
Subrack
Number Part Number Revision Number Serial Number
PS Module
PS Module