User's Manual
Table Of Contents
- UltraWAVE Micro BTS Installation and Commissioning Guide
- Chapter 1 - Unpacking and Configuration Verification
- Chapter 2 - Installation
- 2.1 Analyzing Site Requirements
- 2.2 Mounting the Micro BTS Chassis
- 2.3 Configuring the E1 or T1 Trunk Card
- 2.4 Connecting Ground Cables
- 2.5 Connecting Power Supplies
- 2.6 Connecting E1 or T1 Trunk Cables
- 2.7 Connecting Antennas
- 2.8 Connecting External Alarms
- 2.9 Making a Serial Connection to the Processor Card
- 2.10 Network Connections
- 2.11 Post Installation Cabling and Checks
- Chapter 3 - Off-Line Commissioning
- 3.1 Pre Off-Line Commissioning
- 3.2 Off-Line Commissioning of the Micro BTS
- 3.2.1 Starting XWindows Using the Craft PC
- 3.2.2 Connecting the Craft PC to the ICP Processor Card
- 3.2.3 Setting Up a Serial Connection via the ICP Processor Card Serial Port
- 3.2.4 Power-On LED Tests
- 3.2.5 Configuring Boot Parameters
- 3.2.6 Setting Up an Ethernet Connection to the ICP Processor Card Ethernet Port
- 3.2.7 Verifying Telnet Communications with the Micro BTS over Ethernet
- 3.3 Software Verification using Craft PC
- 3.3.1 Verifying the Current Software Version and Patch Level
- 3.3.2 Checking the Flash Version Number
- 3.3.3 Running E1 or T1 POST Diagnostics
- 3.3.4 Running TRX POST Diagnostics
- 3.3.5 Reviewing POST Results
- 3.3.6 Rebooting the Micro BTS after Running POST
- 3.3.7 Terminating Serial Communications with the Micro BTS
- 3.3.8 Exiting XWindows on the Craft PC
- 3.4 Upgrading the Micro BTS Software Version (Flash)
- 3.5 Post Off-Line Commissioning
- Chapter 4 - Off-Line Commissioning of a Daisy Chain
- Chapter 5 - On-Line Commissioning
- Checklist 1 - Site Readiness Checklist
- Checklist 2 - Installation Checklist
- Checklist 3 - Commissioning Checklist
- Index
132 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Checklist 2 - Installation Checklist
Unpacking the Micro BTS
1 __ Check for visible damage to shipping materials. Contact Alvarion Customer Ser-
vice if any visible damage is found.
2 __ All parts included per shipping invoice.
3 __ Cross check with site specific data to ensure Micro BTS is correctly configured
with all cards.
Mounting the Micro BTS on a Rack (if applicable)
1 __ Attach mounting brackets to chassis.
2 __ Mount chassis in rack.
3 __ Ground chassis.
4 __ Connect power supply: 110 VAC to 220 VAC, 30 A, 50-60 Hz or -40 VDC to
-60 VDC, 40 A.
Connecting the Micro BTS
1 __ Connect “A Interface” E1 or T1 trunk cables to local telephone provider demarca-
tion.
2 __ Configure E1 or T1 trunk card DIP switch settings.
3 __ Ensure power to BTS is off.
Verifying the MSC-Micro BTS Link
It is the operator’s responsibility to verify that all MSC-Micro BTS E1 or T1 links
are ordered, installed and certified by the local telephone facilities/operator.
Verify bit error rates on a nominal 20 minute soak test on the E1 or T1 A-interface
(end-to-end BER test to include E1or T1 trunk cables). The Micro BTS is now
ready for commissioning tests.
Table C2-3: Power Supply Subrack Equipment
Power Supply
Subrack
Number Part Number Revision Number Serial Number
PS Module
PS Module